Logo von Codexkit Pmbok8 Earned Value

Codexkit Pmbok8 Earned Value

Community
hoavdc
codexkit-pmbok8-earned-value

Calculate and interpret Earned Value Management (EVM) metrics per PMBOK 8 Measurement Performance Domain. Compute SPI, CPI, EAC, ETC, TCPI, and generate variance narratives with corrective action recommendations. Use during project execution to assess schedule and cost performance.

Übersicht

Herausgeberhoavdc
RepositoryCodexKit
Skill-Namecodexkit-pmbok8-earned-value
Sterne
27
Forks
12
Mitgelieferte Dateien
1
LizenzMIT
Links
  • Anweisungen in Markdown

    Eine SKILL.md-Datei, die das Modell bei Bedarf lädt. So werden nur dann Token verbraucht, wenn eine Anfrage tatsächlich dazu passt.

  • Funktioniert mit jedem LLM

    KI-Skills bestehen aus reinem Markdown, nicht aus anbieterspezifischem Code. Daher funktionieren sie mit GPT, Claude, Gemini, Grok oder einem lokalen Modell.

  • 1 mitgelieferte Dateien

    Skripte, Vorlagen und Referenzmaterial, die das Modell bei der Arbeit lesen kann. Die Dateien sind schreibgeschützt und werden niemals ausgeführt.

  • Open Source

    Von hoavdc auf GitHub veröffentlicht. Prüfen Sie den Quellinhalt vor der Installation.

Installation

Installieren Sie den KI-Skill Codexkit Pmbok8 Earned Value in TypingMind, um ihn mit jedem LLM zu nutzen, oder fügen Sie ihn einem anderen Agenten hinzu, der SKILL.md lesen kann.

1

In TypingMind installieren

TypingMind installiert einen Skill direkt aus seinem GitHub-Ordner — liest SKILL.md, bündelt die Ressourcendateien und speichert das Ergebnis lokal.

  1. Öffnen Sie die App und gehen Sie zu Plugins → Skills.
  2. Wählen Sie „Von GitHub installieren“.
  3. Fügen Sie die unten angegebene URL des Skill-Ordners ein und bestätigen Sie.
    https://github.com/hoavdc/CodexKit/tree/main/skills/codexkit-pmbok8-earned-value
  4. Aktivieren Sie den Skill in jedem Chat, in dem er verfügbar sein soll.
Plugins → Skills → Skill anlegen → Über GitHub-URL. Fügen Sie dann die Ordner-URL ein und klicken Sie auf „Weiter“.
2

In einem anderen Agenten installieren

Jeder Agent, der das Agent-Skills-Format lesen kann, kann diesen Skill nutzen — kopieren Sie den Ordner in das Skill-Verzeichnis des jeweiligen Agenten.

Claude Code — .claude/skills
git clone --depth 1 https://github.com/hoavdc/CodexKit.git /tmp/CodexKit
mkdir -p .claude/skills
cp -r /tmp/CodexKit/skills/codexkit-pmbok8-earned-value .claude/skills/codexkit-pmbok8-earned-value
Starten Sie Claude Code nach dem Kopieren neu, damit der neue Skill erkannt wird.

In TypingMind verwenden

Aktivieren Sie Codexkit Pmbok8 Earned Value in einem beliebigen Chat in TypingMind. Den Rest übernimmt das Modell. Name und Beschreibung des Skills stehen im System-Prompt. Sobald eine Anfrage passt, lädt das Modell selbstständig die vollständigen Anweisungen — Sie müssen den Skill nie manuell aufrufen, und er verbraucht erst Token, wenn er tatsächlich genutzt wird.

Das Modell lädt Codexkit Pmbok8 Earned Value automatisch, sobald eine passende Anfrage gestellt wird.

Funktioniert mit jedem KI-Modell

KI-Skills bestehen aus reinen Markdown-Anweisungen statt aus anbieterspezifischem Code. Daher ist Codexkit Pmbok8 Earned Value nicht an das Modell gebunden, für das der Skill geschrieben wurde. Installieren Sie ihn einmal in TypingMind und nutzen Sie ihn mit GPT-5, Claude, Gemini, Grok, DeepSeek, Mistral, Llama oder einem selbst betriebenen lokalen Modell — alles mit Ihren eigenen API-Keys.

  • Wird nur bei Bedarf geladen

    Der System-Prompt enthält nur den Namen und die Beschreibung. Die Anweisungen werden bei der ersten passenden Anfrage geladen. Ein ungenutzter Skill verursacht daher keine Kosten.

  • Modell im laufenden Chat wechseln

    Da der Skill aus Anweisungen statt aus Code besteht, funktioniert er auch nach einem Modellwechsel — das nächste Modell liest dieselbe SKILL.md-Datei.

Skill-Anweisungen

Dies ist der Inhalt von SKILL.md, den das Modell lädt. Lesen Sie ihn vor der Installation — ein Skill besteht aus Anweisungen, denen Ihr Modell folgt.

Earned Value Management Analyst

When to Use

  • During project execution when tracking schedule and cost performance
  • At monthly or sprint-end status reporting cycles
  • When stakeholders need objective performance data beyond percentage-complete guesses
  • When forecasting final project cost (EAC) using multiple methods

Procedure

Step 1 — Collect Baseline Data

  1. Confirm Budget at Completion (BAC)
  2. Record Planned Value (PV) at the reporting date
  3. Record Earned Value (EV) — value of work actually completed
  4. Record Actual Cost (AC) — money spent to date

Step 2 — Calculate Core Metrics

MetricFormulaInterpretation
SVEV − PV< 0 = behind schedule
CVEV − AC< 0 = over budget
SPIEV / PV< 1.0 = behind schedule
CPIEV / AC< 1.0 = over budget

Step 3 — Forecast Completion

MethodFormulaWhen to Use
EAC (typical)BAC / CPICurrent CPI trend continues
EAC (atypical)AC + (BAC − EV)Variance was one-time
EAC (SPI×CPI)AC + (BAC − EV) / (CPI × SPI)Both schedule and cost pressure
ETCEAC − ACRemaining spend
TCPI (BAC)(BAC − EV) / (BAC − AC)Efficiency needed to hit BAC
TCPI (EAC)(BAC − EV) / (EAC − AC)Efficiency needed to hit new EAC
VACBAC − EACForecast variance at completion

Step 4 — Generate Narrative

  1. Summarize performance in plain language (ahead/behind, over/under)
  2. Apply traffic-light rating: SPI/CPI ≥ 0.95 = 🟢, 0.8–0.94 = 🟡, < 0.8 = 🔴
  3. Recommend corrective actions for any metric in 🟡 or 🔴 zone
  4. Note trends by comparing with previous period metrics

Inputs

InputRequiredFormat
BAC (total budget)YesCurrency amount
PV (planned value to date)YesCurrency amount
EV (earned value to date)YesCurrency amount
AC (actual cost to date)YesCurrency amount
Prior period SPI/CPIRecommendedDecimal (for trend)

Output

markdown
## EVM Status Report — [Project Name] — Period [X]

### Performance Summary

| Metric | Value | Status |
|--------|-------|--------|
| BAC | $500,000 | — |
| PV | $200,000 | — |
| EV | $180,000 | — |
| AC | $210,000 | — |
| SV | -$20,000 | 🟡 Behind schedule |
| CV | -$30,000 | 🔴 Over budget |
| SPI | 0.90 | 🟡 |
| CPI | 0.86 | 🔴 |

### Forecast

| Method | EAC | VAC |
|--------|-----|-----|
| Typical (CPI trend) | $581,395 | -$81,395 |
| Atypical (one-time) | $530,000 | -$30,000 |
| SPI×CPI compound | $612,745 | -$112,745 |

### TCPI
- To hit BAC: **1.10** (achievable with corrective action)
- To hit EAC: **0.86** (current pace)

### Corrective Actions
1. CPI 🔴: Review scope for non-essential deliverables to reduce remaining cost
2. SPI 🟡: Fast-track critical path activities in next 2 sprints
3. Escalate to sponsor if CPI does not improve to 0.95 by Period X+2

Definition of Done

  • All 7 EVM metrics calculated correctly
  • At least 2 EAC methods presented
  • Traffic-light status applied to SPI and CPI
  • Corrective actions provided for any metric in 🟡 or 🔴
  • Narrative is in plain language (not just formulas)

Examples

Prompt

text
My project has BAC = $500,000. As of end of Month 4:
PV = $200,000, EV = $180,000, AC = $210,000.
Last month SPI was 0.93, CPI was 0.89.
Generate a full EVM report with forecasts and corrective actions.

Quality Criteria

  • Data sources and assumptions are explicitly stated
  • Calculations are reproducible from provided inputs
  • Visualizations or tables have clear labels, units, and time ranges
  • Caveats and confidence levels are documented for estimates

Verification (4C)

CheckQuestion
CorrectnessAre formulas, aggregations, and statistical methods applied correctly?
CompletenessDoes the analysis cover all requested metrics and time ranges?
Context-fitAre the chosen metrics relevant to the business question being answered?
ConsequenceIf this data were used for a decision today, what blind spots remain?

Edge Cases

  • Missing or incomplete data — Document gaps and their potential impact on conclusions. Provide ranges instead of point estimates.
  • Outliers skewing results — Report with and without outliers. Document the decision to include or exclude.
  • Changing data definitions mid-period — Split analysis at the change boundary and note the schema difference.

Changelog

  • v1.0.0 — Initial release

Mitgelieferte Dateien

Das Modell liest diese Dateien bei Bedarf, während der Skill geladen ist. Sie werden als lesbare Dateien bereitgestellt und niemals ausgeführt.

Häufig gestellte Fragen

Was macht der KI-Skill Codexkit Pmbok8 Earned Value?

Calculate and interpret Earned Value Management (EVM) metrics per PMBOK 8 Measurement Performance Domain. Compute SPI, CPI, EAC, ETC, TCPI, and generate variance narratives with corrective action recommendations. Use during project execution to assess schedule and cost performance.

Warum Codexkit Pmbok8 Earned Value in TypingMind nutzen?

Weil Sie den Skill einmal installieren und mit jedem Modell verwenden können. Codexkit Pmbok8 Earned Value besteht aus reinem Markdown statt aus anbieterspezifischem Code. So funktioniert derselbe Skill mit GPT-5, Claude, Gemini, Grok oder einem lokalen Modell – und Sie können das Modell mitten im Chat wechseln, ohne dass der Skill seine Funktion verliert. TypingMind verwendet Ihre eigenen API-Schlüssel. Sie bezahlen die Anbieter daher direkt statt über ein Abonnement pro Nutzerplatz, und Ihre Skills und Chats bleiben in Ihrem eigenen Speicher.

Wie installiere ich Codexkit Pmbok8 Earned Value in TypingMind?

Öffnen Sie in TypingMind Plugins → Skills → Von GitHub installieren und fügen Sie https://github.com/hoavdc/CodexKit/tree/main/skills/codexkit-pmbok8-earned-value ein. TypingMind liest die Datei SKILL.md, bündelt die zugehörigen Dateien und installiert alles als Skill, den Sie für jeden Chat einzeln aktivieren können.

Welche KI-Modelle können Codexkit Pmbok8 Earned Value nutzen?

Jedes Modell, das Sie in TypingMind verbinden. KI-Skills bestehen aus reinen Markdown-Anweisungen statt aus anbieterspezifischem Code. Daher können GPT, Claude, Gemini, Grok und lokale Modelle diesen Skill laden, wenn eine Anfrage dazu passt.

Wie viele KI-Modelle kann ich mit Codexkit Pmbok8 Earned Value verwenden?

So viele Sie möchten. Solange ein Modell Skills unterstützt, können Sie Codexkit Pmbok8 Earned Value damit verwenden – GPT, Claude, Gemini, Grok, DeepSeek, Mistral, Llama und weitere – alles in TypingMind mit Ihren eigenen API-Schlüsseln.

Ist der KI-Skill Codexkit Pmbok8 Earned Value kostenlos?

Ja. Der Skill wird von hoavdc auf GitHub unter der Lizenz MIT veröffentlicht. Sie bezahlen nur Ihren eigenen KI-Anbieter für die verwendeten Token.

Was sind KI-Skills?

Ein KI-Skill ist ein wiederverwendbares Anweisungspaket, das einem KI-Modell vermittelt, wie es eine bestimmte Aufgabe erledigt. Es folgt dem offenen Format Agent Skills: eine Datei namens SKILL.md mit einem Namen und einer Beschreibung sowie allen Skripten, Vorlagen oder Referenzdateien, die das Modell möglicherweise benötigt. Das Modell liest die Anweisungen nur, wenn Ihre Anfrage zum Skill passt. Ein installierter Skill verursacht daher erst Kosten, wenn er verwendet wird.

Wie unterscheiden sich KI-Skills von Plugins oder MCP-Servern?

Ein Plugin oder MCP-Server stellt einem Modell neue aufrufbare Tools bereit – Code, der auf einem System ausgeführt wird und ein Ergebnis zurückgibt. Ein KI-Skill vermittelt dem Modell stattdessen Wissen und Vorgehensweisen: wie es eine Aufgabe angeht, welche Schritte es befolgt und wie eine gute Ausgabe aussieht. Skills bestehen aus reinem Markdown und benötigen daher weder Server noch API-Schlüssel oder Laufzeitumgebung. Sie funktionieren mit jedem Modell.

Alle

Jetzt eigenen KI-Arbeitsbereich einrichten

Abonnieren Sie unseren Newsletter und erfahren Sie mehr über neue Funktionen und kommende Gewinnspiele 👇