Calculate and interpret Earned Value Management (EVM) metrics per PMBOK 8 Measurement Performance Domain. Compute SPI, CPI, EAC, ETC, TCPI, and generate variance narratives with corrective action recommendations. Use during project execution to assess schedule and cost performance.

Iwwersiicht

Editeurhoavdc
RepositoryCodexKit
Skill-Nummcodexkit-pmbok8-earned-value
Stären
27
Forks
12
Matgeliwwert Fichieren
1
LizenzMIT
Linken
  • Instruktiounen am Markdown-Format

    Eng SKILL.md-Datei, déi de Modell bei Bedarf luet, soudatt nëmmen Token ufalen, wann eng Ufro tatsächlech dozou passt.

  • Funktionéiert mat all LLM

    KI-Skills si reng Markdown, keen ubidderspezifesche Code. Dofir funktionéiert dëse Skill mat GPT, Claude, Gemini, Grok oder engem lokale Modell.

  • 1 matgeliwwert Dateien

    Skripten, Virlagen a Referenzen, déi de Modell beim Schaffe liese kann. D'Dateie kënnen nëmme gelies ginn a ginn ni ausgeféiert.

  • Open Source

    Vum hoavdc op GitHub verëffentlecht. Liest de Quelltext, ier Dir de Skill installéiert.

Installatioun

Installéiert de KI-Skill Codexkit Pmbok8 Earned Value an TypingMind, fir e mat all LLM ze benotzen, oder füügt en an en anere KI-Agent an, deen SKILL.md liest.

1

An TypingMind installéieren

TypingMind installéiert e Skill direkt aus sengem GitHub-Dossier — dobäi gëtt SKILL.md gelies, d'Ressourcedateie gi gebëndelt an d'Resultat gëtt lokal gespäichert.

  1. Maacht d'App op a gitt op Plugins → Skills.
  2. Wielt „Vun GitHub installéieren“.
  3. Pecht d'URL vum Skill-Dossier hei drënner an a bestätegt.
    https://github.com/hoavdc/CodexKit/tree/main/skills/codexkit-pmbok8-earned-value
  4. Aktivéiert de Skill an all Chat, an deem Dir e benotze wëllt.
Plugins → Skills → Skill afügen → Vu GitHub-URL, pecht dann d'URL vum Dossier an a klickt op Weider.
2

An engem anere KI-Agent installéieren

All KI-Agent, deen d'Format Agent Skills liest, kann dëse Skill benotzen — kopéiert den Dossier an de Skill-Verzeechnes vun deem KI-Agent.

Claude Code — .claude/skills
git clone --depth 1 https://github.com/hoavdc/CodexKit.git /tmp/CodexKit
mkdir -p .claude/skills
cp -r /tmp/CodexKit/skills/codexkit-pmbok8-earned-value .claude/skills/codexkit-pmbok8-earned-value
Start Claude Code nom Kopéieren nei, fir datt den neie Skill erkannt gëtt.

An TypingMind benotzen

Aktivéiert Codexkit Pmbok8 Earned Value an engem Chat vun TypingMind, an de Modell iwwerhëlt de Rescht. Den Numm an d'Beschreiwung stinn am System-Prompt. Soubal eng Ufro dozou passt, luet de Modell déi komplett Instruktioune selwer — Dir musst de Skill ni manuell opruffen, an et fale keng Token un, bis en tatsächlech benotzt gëtt.

De Modell luet Codexkit Pmbok8 Earned Value automatesch, soubal eng Ufro dozou passt.

Funktionéiert mat all KI-Modell

KI-Skills si reng Markdown-Instruktiounen amplaz vun ubidderspezifeschem Code. Dofir ass Codexkit Pmbok8 Earned Value net un de Modell gebonnen, fir deen de Skill geschriwwe gouf. Installéiert en eemol an TypingMind a benotzt e mat GPT-5, Claude, Gemini, Grok, DeepSeek, Mistral, Llama oder engem lokale Modell, deen Dir selwer bedreift — alles mat Ären eegenen API-Keys.

  • Gëtt nëmme gelueden, wann et néideg ass

    De System-Prompt enthält nëmmen den Numm an d'Beschreiwung. D'Instruktioune gi bei der éischter passender Ufro gelueden, soudatt en onbenotzte Skill näischt kascht.

  • De Modell am lafende Chat wiesselen

    Well de Skill aus Instruktiounen amplaz vu Code besteet, funktionéiert en och no engem Modellwiessel — den nächste Modell liest déi selwecht SKILL.md-Datei.

Skill-Instruktiounen

Dëst ass den Inhalt vu SKILL.md, deen de Modell luet. Liest e virun der Installatioun — e Skill besteet aus Instruktiounen, déi Äre Modell befollegt.

Earned Value Management Analyst

When to Use

  • During project execution when tracking schedule and cost performance
  • At monthly or sprint-end status reporting cycles
  • When stakeholders need objective performance data beyond percentage-complete guesses
  • When forecasting final project cost (EAC) using multiple methods

Procedure

Step 1 — Collect Baseline Data

  1. Confirm Budget at Completion (BAC)
  2. Record Planned Value (PV) at the reporting date
  3. Record Earned Value (EV) — value of work actually completed
  4. Record Actual Cost (AC) — money spent to date

Step 2 — Calculate Core Metrics

MetricFormulaInterpretation
SVEV − PV< 0 = behind schedule
CVEV − AC< 0 = over budget
SPIEV / PV< 1.0 = behind schedule
CPIEV / AC< 1.0 = over budget

Step 3 — Forecast Completion

MethodFormulaWhen to Use
EAC (typical)BAC / CPICurrent CPI trend continues
EAC (atypical)AC + (BAC − EV)Variance was one-time
EAC (SPI×CPI)AC + (BAC − EV) / (CPI × SPI)Both schedule and cost pressure
ETCEAC − ACRemaining spend
TCPI (BAC)(BAC − EV) / (BAC − AC)Efficiency needed to hit BAC
TCPI (EAC)(BAC − EV) / (EAC − AC)Efficiency needed to hit new EAC
VACBAC − EACForecast variance at completion

Step 4 — Generate Narrative

  1. Summarize performance in plain language (ahead/behind, over/under)
  2. Apply traffic-light rating: SPI/CPI ≥ 0.95 = 🟢, 0.8–0.94 = 🟡, < 0.8 = 🔴
  3. Recommend corrective actions for any metric in 🟡 or 🔴 zone
  4. Note trends by comparing with previous period metrics

Inputs

InputRequiredFormat
BAC (total budget)YesCurrency amount
PV (planned value to date)YesCurrency amount
EV (earned value to date)YesCurrency amount
AC (actual cost to date)YesCurrency amount
Prior period SPI/CPIRecommendedDecimal (for trend)

Output

markdown
## EVM Status Report — [Project Name] — Period [X]

### Performance Summary

| Metric | Value | Status |
|--------|-------|--------|
| BAC | $500,000 | — |
| PV | $200,000 | — |
| EV | $180,000 | — |
| AC | $210,000 | — |
| SV | -$20,000 | 🟡 Behind schedule |
| CV | -$30,000 | 🔴 Over budget |
| SPI | 0.90 | 🟡 |
| CPI | 0.86 | 🔴 |

### Forecast

| Method | EAC | VAC |
|--------|-----|-----|
| Typical (CPI trend) | $581,395 | -$81,395 |
| Atypical (one-time) | $530,000 | -$30,000 |
| SPI×CPI compound | $612,745 | -$112,745 |

### TCPI
- To hit BAC: **1.10** (achievable with corrective action)
- To hit EAC: **0.86** (current pace)

### Corrective Actions
1. CPI 🔴: Review scope for non-essential deliverables to reduce remaining cost
2. SPI 🟡: Fast-track critical path activities in next 2 sprints
3. Escalate to sponsor if CPI does not improve to 0.95 by Period X+2

Definition of Done

  • All 7 EVM metrics calculated correctly
  • At least 2 EAC methods presented
  • Traffic-light status applied to SPI and CPI
  • Corrective actions provided for any metric in 🟡 or 🔴
  • Narrative is in plain language (not just formulas)

Examples

Prompt

text
My project has BAC = $500,000. As of end of Month 4:
PV = $200,000, EV = $180,000, AC = $210,000.
Last month SPI was 0.93, CPI was 0.89.
Generate a full EVM report with forecasts and corrective actions.

Quality Criteria

  • Data sources and assumptions are explicitly stated
  • Calculations are reproducible from provided inputs
  • Visualizations or tables have clear labels, units, and time ranges
  • Caveats and confidence levels are documented for estimates

Verification (4C)

CheckQuestion
CorrectnessAre formulas, aggregations, and statistical methods applied correctly?
CompletenessDoes the analysis cover all requested metrics and time ranges?
Context-fitAre the chosen metrics relevant to the business question being answered?
ConsequenceIf this data were used for a decision today, what blind spots remain?

Edge Cases

  • Missing or incomplete data — Document gaps and their potential impact on conclusions. Provide ranges instead of point estimates.
  • Outliers skewing results — Report with and without outliers. Document the decision to include or exclude.
  • Changing data definitions mid-period — Split analysis at the change boundary and note the schema difference.

Changelog

  • v1.0.0 — Initial release

Matgeliwwert Fichieren

De Modell liest dës Dateie bei Bedarf, wärend de Skill gelueden ass. Si ginn als liesbar Dateie bereetgestallt a ginn ni ausgeféiert.

Heefeg gestallte Froen

Wat mécht de KI-Skill Codexkit Pmbok8 Earned Value?

Calculate and interpret Earned Value Management (EVM) metrics per PMBOK 8 Measurement Performance Domain. Compute SPI, CPI, EAC, ETC, TCPI, and generate variance narratives with corrective action recommendations. Use during project execution to assess schedule and cost performance.

Firwat Codexkit Pmbok8 Earned Value op TypingMind benotzen?

Well Dir en eemol installéiert a mat all Modell benotze kënnt. Codexkit Pmbok8 Earned Value besteet aus einfachem Markdown amplaz vun ubidderspezifeschem Code. Dee selwechte Skill funktionéiert also mat GPT-5, Claude, Gemini, Grok oder engem lokale Modell – an Dir kënnt de Modell matzen am Chat wiesselen, ouni datt de Skill ophält ze funktionéieren. TypingMind benotzt Är eegen API-Schlësselen, sou datt Dir d'Ubidder direkt bezuelt amplaz vun engem Abonnement pro Benotzerplaz. Är Skills a Chats bleiwen an Ärem eegene Späicher.

Wéi installéieren ech Codexkit Pmbok8 Earned Value an TypingMind?

Maacht an TypingMind Plugins → Skills → Vu GitHub installéieren op a setzt https://github.com/hoavdc/CodexKit/tree/main/skills/codexkit-pmbok8-earned-value an. TypingMind liest d'Datei SKILL.md, bündelt déi zougehéiereg Dateien an installéiert dat Ganzt als Skill, deen Dir pro Chat aktivéiere kënnt.

Wéi eng KI-Modeller kënnen Codexkit Pmbok8 Earned Value benotzen?

All Modell, deen Dir an TypingMind verbënnt. KI-Skills sinn einfach Markdown-Instruktiounen an net ubidderspezifesche Code. Dofir kënne GPT, Claude, Gemini, Grok a lokal Modeller dëse Skill lueden, wann eng Ufro dozou passt.

Wéi vill KI-Modeller kann ech mat Codexkit Pmbok8 Earned Value benotzen?

Esou vill Dir wëllt. Soulaang e Modell Skills ënnerstëtzt, kënnt Dir Codexkit Pmbok8 Earned Value domat benotzen – GPT, Claude, Gemini, Grok, DeepSeek, Mistral, Llama a méi – alles op TypingMind mat Ären eegenen API-Schlësselen.

Ass de KI-Skill Codexkit Pmbok8 Earned Value gratis?

Jo. De Skill gëtt vum hoavdc ënner der Lizenz MIT op GitHub publizéiert. Dir bezuelt nëmmen Ären eegene KI-Ubidder fir d'Token, déi Dir benotzt.

Wat si KI-Skills?

E KI-Skill ass e weiderverwendbaart Pak vun Instruktiounen, dat engem KI-Modell bäibréngt, wéi en eng bestëmmt Aufgab erfëllt. E follegt dem oppenen Agent Skills-Format: eng Datei SKILL.md mat engem Numm an enger Beschreiwung, plus all Scripten, Virlagen oder Referenzdateien, déi de Modell eventuell brauch. De Modell liest d'Instruktiounen eréischt, wann Är Ufro zum Skill passt. En installéierte Skill kascht also näischt, bis e benotzt gëtt.

Wéi ënnerscheede sech KI-Skills vu Plugins oder MCP-Serveren?

E Plugin oder MCP-Server gëtt engem Modell nei Tools, déi en opruffe kann – Code, deen iergendwou leeft an e Resultat zeréckgëtt. E KI-Skill gëtt dem Modell dogéint Wëssen an eng Virgoensweis: wéi en eng Aufgab ugeet, wéi eng Schrëtt en nokënnt a wéi eng gutt Ausgab ausgesäit. Skills bestinn aus einfachem Markdown, brauche kee Server, keen API-Schlëssel a keng Lafzäitëmfeld a funktionéiere mat all Modell.

All weisen

Elo Ären eegene KI-Workspace ariichten

Abonnéiert Iech op eisen Newsletter, fir iwwer nei Funktiounen an zukünfteg Gewënnspiller informéiert ze ginn 👇