Analyze schedule delays, identify causes, and calculate time impacts using delay analysis methods.

Iwwersiicht

Editeurdatadrivenconstruction
RepositoryDDC_Skills_for_AI_Agents_in_Construction
Skill-Nummschedule-delay-analyzer
Stären
365
Forks
91
Matgeliwwert Fichieren
2
LizenzMIT
Linken
  • Instruktiounen am Markdown-Format

    Eng SKILL.md-Datei, déi de Modell bei Bedarf luet, soudatt nëmmen Token ufalen, wann eng Ufro tatsächlech dozou passt.

  • Funktionéiert mat all LLM

    KI-Skills si reng Markdown, keen ubidderspezifesche Code. Dofir funktionéiert dëse Skill mat GPT, Claude, Gemini, Grok oder engem lokale Modell.

  • 2 matgeliwwert Dateien

    Skripten, Virlagen a Referenzen, déi de Modell beim Schaffe liese kann. D'Dateie kënnen nëmme gelies ginn a ginn ni ausgeféiert.

  • Open Source

    Vum datadrivenconstruction op GitHub verëffentlecht. Liest de Quelltext, ier Dir de Skill installéiert.

Installatioun

Installéiert de KI-Skill Schedule Delay Analyzer an TypingMind, fir e mat all LLM ze benotzen, oder füügt en an en anere KI-Agent an, deen SKILL.md liest.

1

An TypingMind installéieren

TypingMind installéiert e Skill direkt aus sengem GitHub-Dossier — dobäi gëtt SKILL.md gelies, d'Ressourcedateie gi gebëndelt an d'Resultat gëtt lokal gespäichert.

  1. Maacht d'App op a gitt op Plugins → Skills.
  2. Wielt „Vun GitHub installéieren“.
  3. Pecht d'URL vum Skill-Dossier hei drënner an a bestätegt.
    https://github.com/datadrivenconstruction/DDC_Skills_for_AI_Agents_in_Construction/tree/main/1_DDC_Toolkit/Schedule-Management/schedule-delay-analyzer
  4. Aktivéiert de Skill an all Chat, an deem Dir e benotze wëllt.
Plugins → Skills → Skill afügen → Vu GitHub-URL, pecht dann d'URL vum Dossier an a klickt op Weider.
2

An engem anere KI-Agent installéieren

All KI-Agent, deen d'Format Agent Skills liest, kann dëse Skill benotzen — kopéiert den Dossier an de Skill-Verzeechnes vun deem KI-Agent.

Claude Code — .claude/skills
git clone --depth 1 https://github.com/datadrivenconstruction/DDC_Skills_for_AI_Agents_in_Construction.git /tmp/DDC_Skills_for_AI_Agents_in_Construction
mkdir -p .claude/skills
cp -r /tmp/DDC_Skills_for_AI_Agents_in_Construction/1_DDC_Toolkit/Schedule-Management/schedule-delay-analyzer .claude/skills/schedule-delay-analyzer
Start Claude Code nom Kopéieren nei, fir datt den neie Skill erkannt gëtt.

An TypingMind benotzen

Aktivéiert Schedule Delay Analyzer an engem Chat vun TypingMind, an de Modell iwwerhëlt de Rescht. Den Numm an d'Beschreiwung stinn am System-Prompt. Soubal eng Ufro dozou passt, luet de Modell déi komplett Instruktioune selwer — Dir musst de Skill ni manuell opruffen, an et fale keng Token un, bis en tatsächlech benotzt gëtt.

De Modell luet Schedule Delay Analyzer automatesch, soubal eng Ufro dozou passt.

Funktionéiert mat all KI-Modell

KI-Skills si reng Markdown-Instruktiounen amplaz vun ubidderspezifeschem Code. Dofir ass Schedule Delay Analyzer net un de Modell gebonnen, fir deen de Skill geschriwwe gouf. Installéiert en eemol an TypingMind a benotzt e mat GPT-5, Claude, Gemini, Grok, DeepSeek, Mistral, Llama oder engem lokale Modell, deen Dir selwer bedreift — alles mat Ären eegenen API-Keys.

  • Gëtt nëmme gelueden, wann et néideg ass

    De System-Prompt enthält nëmmen den Numm an d'Beschreiwung. D'Instruktioune gi bei der éischter passender Ufro gelueden, soudatt en onbenotzte Skill näischt kascht.

  • De Modell am lafende Chat wiesselen

    Well de Skill aus Instruktiounen amplaz vu Code besteet, funktionéiert en och no engem Modellwiessel — den nächste Modell liest déi selwecht SKILL.md-Datei.

Skill-Instruktiounen

Dëst ass den Inhalt vu SKILL.md, deen de Modell luet. Liest e virun der Installatioun — e Skill besteet aus Instruktiounen, déi Äre Modell befollegt.

Schedule Delay Analyzer

Technical Implementation

python
import pandas as pd
from datetime import date, timedelta
from typing import Dict, Any, List, Optional
from dataclasses import dataclass, field
from enum import Enum


class DelayType(Enum):
    EXCUSABLE_COMPENSABLE = "excusable_compensable"
    EXCUSABLE_NON_COMPENSABLE = "excusable_non_compensable"
    NON_EXCUSABLE = "non_excusable"
    CONCURRENT = "concurrent"


class DelayCause(Enum):
    OWNER_CHANGE = "owner_change"
    DESIGN_ERROR = "design_error"
    WEATHER = "weather"
    DIFFERING_CONDITIONS = "differing_conditions"
    CONTRACTOR_ISSUE = "contractor_issue"
    MATERIAL_DELAY = "material_delay"
    LABOR_SHORTAGE = "labor_shortage"
    PERMIT_DELAY = "permit_delay"
    OTHER = "other"


@dataclass
class DelayEvent:
    delay_id: str
    activity_id: str
    activity_name: str
    delay_type: DelayType
    cause: DelayCause
    start_date: date
    end_date: date
    delay_days: int
    on_critical_path: bool
    description: str
    documentation: List[str] = field(default_factory=list)
    cost_impact: float = 0.0


@dataclass
class ScheduleBaseline:
    baseline_date: date
    planned_completion: date
    activities: Dict[str, Dict[str, date]]  # activity_id: {start, end}


class ScheduleDelayAnalyzer:
    def __init__(self, project_name: str, contract_completion: date):
        self.project_name = project_name
        self.contract_completion = contract_completion
        self.baselines: List[ScheduleBaseline] = []
        self.delays: Dict[str, DelayEvent] = {}
        self._counter = 0

    def add_baseline(self, baseline_date: date, planned_completion: date,
                    activities: Dict[str, Dict[str, date]]):
        baseline = ScheduleBaseline(baseline_date, planned_completion, activities)
        self.baselines.append(baseline)

    def record_delay(self, activity_id: str, activity_name: str,
                    delay_type: DelayType, cause: DelayCause,
                    start_date: date, end_date: date,
                    on_critical_path: bool, description: str,
                    cost_impact: float = 0) -> DelayEvent:
        self._counter += 1
        delay_id = f"DLY-{self._counter:04d}"

        delay = DelayEvent(
            delay_id=delay_id,
            activity_id=activity_id,
            activity_name=activity_name,
            delay_type=delay_type,
            cause=cause,
            start_date=start_date,
            end_date=end_date,
            delay_days=(end_date - start_date).days,
            on_critical_path=on_critical_path,
            description=description,
            cost_impact=cost_impact
        )
        self.delays[delay_id] = delay
        return delay

    def calculate_project_delay(self) -> int:
        """Calculate total critical path delay."""
        critical_delays = [d for d in self.delays.values() if d.on_critical_path]
        return sum(d.delay_days for d in critical_delays)

    def analyze_by_type(self) -> Dict[str, Dict[str, Any]]:
        analysis = {}
        for delay in self.delays.values():
            dtype = delay.delay_type.value
            if dtype not in analysis:
                analysis[dtype] = {'count': 0, 'days': 0, 'cost': 0}
            analysis[dtype]['count'] += 1
            analysis[dtype]['days'] += delay.delay_days
            analysis[dtype]['cost'] += delay.cost_impact
        return analysis

    def analyze_by_cause(self) -> Dict[str, int]:
        by_cause = {}
        for delay in self.delays.values():
            cause = delay.cause.value
            by_cause[cause] = by_cause.get(cause, 0) + delay.delay_days
        return by_cause

    def calculate_time_extension_claim(self) -> Dict[str, Any]:
        """Calculate basis for time extension claim."""
        excusable = [d for d in self.delays.values()
                    if d.delay_type in [DelayType.EXCUSABLE_COMPENSABLE,
                                        DelayType.EXCUSABLE_NON_COMPENSABLE]
                    and d.on_critical_path]

        compensable = [d for d in excusable
                      if d.delay_type == DelayType.EXCUSABLE_COMPENSABLE]

        return {
            'excusable_delays': len(excusable),
            'excusable_days': sum(d.delay_days for d in excusable),
            'compensable_delays': len(compensable),
            'compensable_days': sum(d.delay_days for d in compensable),
            'total_cost_impact': sum(d.cost_impact for d in compensable),
            'recommended_extension': sum(d.delay_days for d in excusable)
        }

    def get_summary(self) -> Dict[str, Any]:
        critical_delay = self.calculate_project_delay()
        projected_completion = self.contract_completion + timedelta(days=critical_delay)

        return {
            'project': self.project_name,
            'contract_completion': self.contract_completion,
            'projected_completion': projected_completion,
            'total_delays': len(self.delays),
            'critical_path_delays': sum(1 for d in self.delays.values() if d.on_critical_path),
            'total_delay_days': critical_delay,
            'by_type': self.analyze_by_type(),
            'by_cause': self.analyze_by_cause()
        }

    def export_analysis(self, output_path: str):
        data = [{
            'ID': d.delay_id,
            'Activity': d.activity_name,
            'Type': d.delay_type.value,
            'Cause': d.cause.value,
            'Start': d.start_date,
            'End': d.end_date,
            'Days': d.delay_days,
            'Critical': d.on_critical_path,
            'Cost Impact': d.cost_impact,
            'Description': d.description
        } for d in self.delays.values()]
        pd.DataFrame(data).to_excel(output_path, index=False)

Quick Start

python
analyzer = ScheduleDelayAnalyzer("Office Tower", date(2024, 12, 31))

delay = analyzer.record_delay(
    activity_id="A-300",
    activity_name="Foundation Work",
    delay_type=DelayType.EXCUSABLE_COMPENSABLE,
    cause=DelayCause.OWNER_CHANGE,
    start_date=date(2024, 3, 1),
    end_date=date(2024, 3, 15),
    on_critical_path=True,
    description="Owner requested additional scope",
    cost_impact=50000
)

summary = analyzer.get_summary()
print(f"Project delayed by {summary['total_delay_days']} days")

claim = analyzer.calculate_time_extension_claim()
print(f"Recommended extension: {claim['recommended_extension']} days")

Resources

  • DDC Book: Chapter 3.3 - Schedule Management

Matgeliwwert Fichieren

De Modell liest dës Dateie bei Bedarf, wärend de Skill gelueden ass. Si ginn als liesbar Dateie bereetgestallt a ginn ni ausgeféiert.

Heefeg gestallte Froen

Wat mécht de KI-Skill Schedule Delay Analyzer?

Analyze schedule delays, identify causes, and calculate time impacts using delay analysis methods.

Firwat Schedule Delay Analyzer op TypingMind benotzen?

Well Dir en eemol installéiert a mat all Modell benotze kënnt. Schedule Delay Analyzer besteet aus einfachem Markdown amplaz vun ubidderspezifeschem Code. Dee selwechte Skill funktionéiert also mat GPT-5, Claude, Gemini, Grok oder engem lokale Modell – an Dir kënnt de Modell matzen am Chat wiesselen, ouni datt de Skill ophält ze funktionéieren. TypingMind benotzt Är eegen API-Schlësselen, sou datt Dir d'Ubidder direkt bezuelt amplaz vun engem Abonnement pro Benotzerplaz. Är Skills a Chats bleiwen an Ärem eegene Späicher.

Wéi installéieren ech Schedule Delay Analyzer an TypingMind?

Maacht an TypingMind Plugins → Skills → Vu GitHub installéieren op a setzt https://github.com/datadrivenconstruction/DDC_Skills_for_AI_Agents_in_Construction/tree/main/1_DDC_Toolkit/Schedule-Management/schedule-delay-analyzer an. TypingMind liest d'Datei SKILL.md, bündelt déi zougehéiereg Dateien an installéiert dat Ganzt als Skill, deen Dir pro Chat aktivéiere kënnt.

Wéi eng KI-Modeller kënnen Schedule Delay Analyzer benotzen?

All Modell, deen Dir an TypingMind verbënnt. KI-Skills sinn einfach Markdown-Instruktiounen an net ubidderspezifesche Code. Dofir kënne GPT, Claude, Gemini, Grok a lokal Modeller dëse Skill lueden, wann eng Ufro dozou passt.

Wéi vill KI-Modeller kann ech mat Schedule Delay Analyzer benotzen?

Esou vill Dir wëllt. Soulaang e Modell Skills ënnerstëtzt, kënnt Dir Schedule Delay Analyzer domat benotzen – GPT, Claude, Gemini, Grok, DeepSeek, Mistral, Llama a méi – alles op TypingMind mat Ären eegenen API-Schlësselen.

Ass de KI-Skill Schedule Delay Analyzer gratis?

Jo. De Skill gëtt vum datadrivenconstruction ënner der Lizenz MIT op GitHub publizéiert. Dir bezuelt nëmmen Ären eegene KI-Ubidder fir d'Token, déi Dir benotzt.

Wat si KI-Skills?

E KI-Skill ass e weiderverwendbaart Pak vun Instruktiounen, dat engem KI-Modell bäibréngt, wéi en eng bestëmmt Aufgab erfëllt. E follegt dem oppenen Agent Skills-Format: eng Datei SKILL.md mat engem Numm an enger Beschreiwung, plus all Scripten, Virlagen oder Referenzdateien, déi de Modell eventuell brauch. De Modell liest d'Instruktiounen eréischt, wann Är Ufro zum Skill passt. En installéierte Skill kascht also näischt, bis e benotzt gëtt.

Wéi ënnerscheede sech KI-Skills vu Plugins oder MCP-Serveren?

E Plugin oder MCP-Server gëtt engem Modell nei Tools, déi en opruffe kann – Code, deen iergendwou leeft an e Resultat zeréckgëtt. E KI-Skill gëtt dem Modell dogéint Wëssen an eng Virgoensweis: wéi en eng Aufgab ugeet, wéi eng Schrëtt en nokënnt a wéi eng gutt Ausgab ausgesäit. Skills bestinn aus einfachem Markdown, brauche kee Server, keen API-Schlëssel a keng Lafzäitëmfeld a funktionéiere mat all Modell.

All weisen

Elo Ären eegene KI-Workspace ariichten

Abonnéiert Iech op eisen Newsletter, fir iwwer nei Funktiounen an zukünfteg Gewënnspiller informéiert ze ginn 👇