Analyze schedule delays, identify causes, and calculate time impacts using delay analysis methods.

Overview

Publisherdatadrivenconstruction
RepositoryDDC_Skills_for_AI_Agents_in_Construction
Skill nameschedule-delay-analyzer
Stars
365
Forks
91
Bundled files
2
LicenseMIT
Links
  • Markdown instructions

    A SKILL.md file the model loads on demand, so it only costs tokens when a request actually matches.

  • Works with any LLM

    AI skills are plain Markdown, not provider-specific code, so this works with GPT, Claude, Gemini, Grok, or a local model.

  • 2 bundled files

    Scripts, templates, and references the model can read while it works. Files are read-only and never executed.

  • Open source

    Published by datadrivenconstruction on GitHub. Read the source before you install it.

Installation

Install the Schedule Delay Analyzer AI skill in TypingMind to use it with any LLM, or drop it into another agent that reads SKILL.md.

1

Install in TypingMind

TypingMind installs a skill straight from its GitHub folder — it reads SKILL.md, bundles the resource files, and stores the result locally.

  1. Open the app and go to Plugins → Skills.
  2. Choose "Install from GitHub".
  3. Paste the skill folder URL below and confirm.
    https://github.com/datadrivenconstruction/DDC_Skills_for_AI_Agents_in_Construction/tree/main/1_DDC_Toolkit/Schedule-Management/schedule-delay-analyzer
  4. Enable the skill in any chat where you want it available.
Plugins → Skills → Add skill → From GitHub URL, then paste the folder URL and press Continue.
2

Install in another agent

Any agent that reads the Agent Skills format can use this skill — copy the folder into that agent's skills directory.

Claude Code — .claude/skills
git clone --depth 1 https://github.com/datadrivenconstruction/DDC_Skills_for_AI_Agents_in_Construction.git /tmp/DDC_Skills_for_AI_Agents_in_Construction
mkdir -p .claude/skills
cp -r /tmp/DDC_Skills_for_AI_Agents_in_Construction/1_DDC_Toolkit/Schedule-Management/schedule-delay-analyzer .claude/skills/schedule-delay-analyzer
Restart Claude Code after copying so it picks up the new skill.

Use it in TypingMind

Enable Schedule Delay Analyzer in any TypingMind chat and the model takes it from there. Its name and description sit in the system prompt, and the moment a request matches, the model loads the full instructions itself — you never invoke it by hand, and it costs no tokens until it is actually used.

The model loads Schedule Delay Analyzer on its own as soon as a request matches it.

Works with any AI model

AI skills are plain Markdown instructions rather than provider-specific code, so Schedule Delay Analyzer is not tied to the model it was written for. Install it once in TypingMind and use it with GPT-5, Claude, Gemini, Grok, DeepSeek, Mistral, Llama, or a local model you run yourself — all on your own API keys.

  • Loaded only when it is needed

    The system prompt carries just the name and description. The instructions are fetched on the first matching request, so an idle skill costs nothing.

  • Switch models mid-chat

    Because the skill is instructions rather than code, changing model does not break it — the next model reads the same SKILL.md.

Skill instructions

This is the SKILL.md content the model loads. Read it before installing — a skill is instructions your model will follow.

Schedule Delay Analyzer

Technical Implementation

python
import pandas as pd
from datetime import date, timedelta
from typing import Dict, Any, List, Optional
from dataclasses import dataclass, field
from enum import Enum


class DelayType(Enum):
    EXCUSABLE_COMPENSABLE = "excusable_compensable"
    EXCUSABLE_NON_COMPENSABLE = "excusable_non_compensable"
    NON_EXCUSABLE = "non_excusable"
    CONCURRENT = "concurrent"


class DelayCause(Enum):
    OWNER_CHANGE = "owner_change"
    DESIGN_ERROR = "design_error"
    WEATHER = "weather"
    DIFFERING_CONDITIONS = "differing_conditions"
    CONTRACTOR_ISSUE = "contractor_issue"
    MATERIAL_DELAY = "material_delay"
    LABOR_SHORTAGE = "labor_shortage"
    PERMIT_DELAY = "permit_delay"
    OTHER = "other"


@dataclass
class DelayEvent:
    delay_id: str
    activity_id: str
    activity_name: str
    delay_type: DelayType
    cause: DelayCause
    start_date: date
    end_date: date
    delay_days: int
    on_critical_path: bool
    description: str
    documentation: List[str] = field(default_factory=list)
    cost_impact: float = 0.0


@dataclass
class ScheduleBaseline:
    baseline_date: date
    planned_completion: date
    activities: Dict[str, Dict[str, date]]  # activity_id: {start, end}


class ScheduleDelayAnalyzer:
    def __init__(self, project_name: str, contract_completion: date):
        self.project_name = project_name
        self.contract_completion = contract_completion
        self.baselines: List[ScheduleBaseline] = []
        self.delays: Dict[str, DelayEvent] = {}
        self._counter = 0

    def add_baseline(self, baseline_date: date, planned_completion: date,
                    activities: Dict[str, Dict[str, date]]):
        baseline = ScheduleBaseline(baseline_date, planned_completion, activities)
        self.baselines.append(baseline)

    def record_delay(self, activity_id: str, activity_name: str,
                    delay_type: DelayType, cause: DelayCause,
                    start_date: date, end_date: date,
                    on_critical_path: bool, description: str,
                    cost_impact: float = 0) -> DelayEvent:
        self._counter += 1
        delay_id = f"DLY-{self._counter:04d}"

        delay = DelayEvent(
            delay_id=delay_id,
            activity_id=activity_id,
            activity_name=activity_name,
            delay_type=delay_type,
            cause=cause,
            start_date=start_date,
            end_date=end_date,
            delay_days=(end_date - start_date).days,
            on_critical_path=on_critical_path,
            description=description,
            cost_impact=cost_impact
        )
        self.delays[delay_id] = delay
        return delay

    def calculate_project_delay(self) -> int:
        """Calculate total critical path delay."""
        critical_delays = [d for d in self.delays.values() if d.on_critical_path]
        return sum(d.delay_days for d in critical_delays)

    def analyze_by_type(self) -> Dict[str, Dict[str, Any]]:
        analysis = {}
        for delay in self.delays.values():
            dtype = delay.delay_type.value
            if dtype not in analysis:
                analysis[dtype] = {'count': 0, 'days': 0, 'cost': 0}
            analysis[dtype]['count'] += 1
            analysis[dtype]['days'] += delay.delay_days
            analysis[dtype]['cost'] += delay.cost_impact
        return analysis

    def analyze_by_cause(self) -> Dict[str, int]:
        by_cause = {}
        for delay in self.delays.values():
            cause = delay.cause.value
            by_cause[cause] = by_cause.get(cause, 0) + delay.delay_days
        return by_cause

    def calculate_time_extension_claim(self) -> Dict[str, Any]:
        """Calculate basis for time extension claim."""
        excusable = [d for d in self.delays.values()
                    if d.delay_type in [DelayType.EXCUSABLE_COMPENSABLE,
                                        DelayType.EXCUSABLE_NON_COMPENSABLE]
                    and d.on_critical_path]

        compensable = [d for d in excusable
                      if d.delay_type == DelayType.EXCUSABLE_COMPENSABLE]

        return {
            'excusable_delays': len(excusable),
            'excusable_days': sum(d.delay_days for d in excusable),
            'compensable_delays': len(compensable),
            'compensable_days': sum(d.delay_days for d in compensable),
            'total_cost_impact': sum(d.cost_impact for d in compensable),
            'recommended_extension': sum(d.delay_days for d in excusable)
        }

    def get_summary(self) -> Dict[str, Any]:
        critical_delay = self.calculate_project_delay()
        projected_completion = self.contract_completion + timedelta(days=critical_delay)

        return {
            'project': self.project_name,
            'contract_completion': self.contract_completion,
            'projected_completion': projected_completion,
            'total_delays': len(self.delays),
            'critical_path_delays': sum(1 for d in self.delays.values() if d.on_critical_path),
            'total_delay_days': critical_delay,
            'by_type': self.analyze_by_type(),
            'by_cause': self.analyze_by_cause()
        }

    def export_analysis(self, output_path: str):
        data = [{
            'ID': d.delay_id,
            'Activity': d.activity_name,
            'Type': d.delay_type.value,
            'Cause': d.cause.value,
            'Start': d.start_date,
            'End': d.end_date,
            'Days': d.delay_days,
            'Critical': d.on_critical_path,
            'Cost Impact': d.cost_impact,
            'Description': d.description
        } for d in self.delays.values()]
        pd.DataFrame(data).to_excel(output_path, index=False)

Quick Start

python
analyzer = ScheduleDelayAnalyzer("Office Tower", date(2024, 12, 31))

delay = analyzer.record_delay(
    activity_id="A-300",
    activity_name="Foundation Work",
    delay_type=DelayType.EXCUSABLE_COMPENSABLE,
    cause=DelayCause.OWNER_CHANGE,
    start_date=date(2024, 3, 1),
    end_date=date(2024, 3, 15),
    on_critical_path=True,
    description="Owner requested additional scope",
    cost_impact=50000
)

summary = analyzer.get_summary()
print(f"Project delayed by {summary['total_delay_days']} days")

claim = analyzer.calculate_time_extension_claim()
print(f"Recommended extension: {claim['recommended_extension']} days")

Resources

  • DDC Book: Chapter 3.3 - Schedule Management

Bundled files

The model reads these on demand while the skill is loaded. They are exposed as readable files and are never executed.

Frequently asked questions

What does the Schedule Delay Analyzer AI skill do?

Analyze schedule delays, identify causes, and calculate time impacts using delay analysis methods.

Why use Schedule Delay Analyzer on TypingMind?

Because you install it once and use it with any model. Schedule Delay Analyzer is plain Markdown rather than provider-specific code, so the same skill runs on GPT-5, Claude, Gemini, Grok, or a local model — and you can switch model mid-chat without it breaking. TypingMind runs on your own API keys, so you pay providers directly instead of a per-seat subscription, and your skills and chats stay in your own storage.

How do I install Schedule Delay Analyzer in TypingMind?

Open Plugins → Skills → Install from GitHub in TypingMind and paste https://github.com/datadrivenconstruction/DDC_Skills_for_AI_Agents_in_Construction/tree/main/1_DDC_Toolkit/Schedule-Management/schedule-delay-analyzer. TypingMind reads its SKILL.md and bundles its files and installs it as a skill you can enable per chat.

Which AI models can use Schedule Delay Analyzer?

Any model you connect in TypingMind. AI skills are plain Markdown instructions rather than provider-specific code, so GPT, Claude, Gemini, Grok, and local models can all load this skill when a request matches it.

How many AI models can I use with Schedule Delay Analyzer?

As many as you like. As long as a model supports skills, you can use Schedule Delay Analyzer with it — GPT, Claude, Gemini, Grok, DeepSeek, Mistral, Llama and more — all on TypingMind with your own API keys.

Is the Schedule Delay Analyzer AI skill free?

Yes. It is published on GitHub by datadrivenconstruction under the MIT license. You only pay your own AI provider for the tokens you use.

What are AI skills?

An AI skill is a reusable instruction bundle that teaches an AI model how to do one specific task. It follows the open Agent Skills format: a SKILL.md file with a name and description, plus any scripts, templates or reference files the model may need. The model reads the instructions only when your request matches the skill, so an installed skill costs nothing until it is used.

How are AI skills different from plugins or MCP servers?

A plugin or MCP server gives a model new tools to call — code that runs somewhere and returns a result. An AI skill gives the model knowledge and process instead: how to approach a task, which steps to follow, what good output looks like. Skills are plain Markdown, so they need no server, no API key and no runtime, and they work with any model.

View all

Set up your own AI workspace now

Get notified about new features and future giveaways by subscribing to our newsletter 👇