Analyze project critical path from schedule data. Identify critical activities, calculate float, and assess schedule risk.

Overview

Publisherdatadrivenconstruction
RepositoryDDC_Skills_for_AI_Agents_in_Construction
Skill namecritical-path-analyzer
Stars
365
Forks
91
Bundled files
2
LicenseMIT
Links
  • Markdown instructions

    A SKILL.md file the model loads on demand, so it only costs tokens when a request actually matches.

  • Works with any LLM

    AI skills are plain Markdown, not provider-specific code, so this works with GPT, Claude, Gemini, Grok, or a local model.

  • 2 bundled files

    Scripts, templates, and references the model can read while it works. Files are read-only and never executed.

  • Open source

    Published by datadrivenconstruction on GitHub. Read the source before you install it.

Installation

Install the Critical Path Analyzer AI skill in TypingMind to use it with any LLM, or drop it into another agent that reads SKILL.md.

1

Install in TypingMind

TypingMind installs a skill straight from its GitHub folder — it reads SKILL.md, bundles the resource files, and stores the result locally.

  1. Open the app and go to Plugins → Skills.
  2. Choose "Install from GitHub".
  3. Paste the skill folder URL below and confirm.
    https://github.com/datadrivenconstruction/DDC_Skills_for_AI_Agents_in_Construction/tree/main/1_DDC_Toolkit/Schedule-Management/critical-path-analyzer
  4. Enable the skill in any chat where you want it available.
Plugins → Skills → Add skill → From GitHub URL, then paste the folder URL and press Continue.
2

Install in another agent

Any agent that reads the Agent Skills format can use this skill — copy the folder into that agent's skills directory.

Claude Code — .claude/skills
git clone --depth 1 https://github.com/datadrivenconstruction/DDC_Skills_for_AI_Agents_in_Construction.git /tmp/DDC_Skills_for_AI_Agents_in_Construction
mkdir -p .claude/skills
cp -r /tmp/DDC_Skills_for_AI_Agents_in_Construction/1_DDC_Toolkit/Schedule-Management/critical-path-analyzer .claude/skills/critical-path-analyzer
Restart Claude Code after copying so it picks up the new skill.

Use it in TypingMind

Enable Critical Path Analyzer in any TypingMind chat and the model takes it from there. Its name and description sit in the system prompt, and the moment a request matches, the model loads the full instructions itself — you never invoke it by hand, and it costs no tokens until it is actually used.

The model loads Critical Path Analyzer on its own as soon as a request matches it.

Works with any AI model

AI skills are plain Markdown instructions rather than provider-specific code, so Critical Path Analyzer is not tied to the model it was written for. Install it once in TypingMind and use it with GPT-5, Claude, Gemini, Grok, DeepSeek, Mistral, Llama, or a local model you run yourself — all on your own API keys.

  • Loaded only when it is needed

    The system prompt carries just the name and description. The instructions are fetched on the first matching request, so an idle skill costs nothing.

  • Switch models mid-chat

    Because the skill is instructions rather than code, changing model does not break it — the next model reads the same SKILL.md.

Skill instructions

This is the SKILL.md content the model loads. Read it before installing — a skill is instructions your model will follow.

Critical Path Analyzer

Business Case

Problem Statement

Schedule management requires understanding:

  • Which activities are critical?
  • How much float exists?
  • What delays impact completion?
  • Where to focus resources?

Solution

Analyze schedule network to identify critical path, calculate float, and provide actionable schedule insights.

Technical Implementation

python
import pandas as pd
import numpy as np
from typing import Dict, Any, List, Optional, Set
from dataclasses import dataclass, field
from datetime import date, timedelta
from enum import Enum
from collections import defaultdict


class ActivityStatus(Enum):
    NOT_STARTED = "not_started"
    IN_PROGRESS = "in_progress"
    COMPLETED = "completed"
    DELAYED = "delayed"


@dataclass
class Activity:
    activity_id: str
    name: str
    duration: int  # days
    predecessors: List[str]
    early_start: int = 0
    early_finish: int = 0
    late_start: int = 0
    late_finish: int = 0
    total_float: int = 0
    free_float: int = 0
    is_critical: bool = False
    status: ActivityStatus = ActivityStatus.NOT_STARTED
    percent_complete: float = 0
    actual_start: Optional[date] = None
    actual_finish: Optional[date] = None


@dataclass
class CriticalPathResult:
    critical_path: List[str]
    project_duration: int
    activities: Dict[str, Activity]
    near_critical: List[str]  # Float < 5 days
    total_float_days: int


class CriticalPathAnalyzer:
    """Analyze project critical path."""

    NEAR_CRITICAL_THRESHOLD = 5  # days

    def __init__(self, project_start: date):
        self.project_start = project_start
        self.activities: Dict[str, Activity] = {}

    def add_activity(self,
                     activity_id: str,
                     name: str,
                     duration: int,
                     predecessors: List[str] = None):
        """Add activity to network."""

        self.activities[activity_id] = Activity(
            activity_id=activity_id,
            name=name,
            duration=duration,
            predecessors=predecessors or []
        )

    def import_from_dataframe(self, df: pd.DataFrame):
        """Import activities from DataFrame."""
        for _, row in df.iterrows():
            preds = row.get('predecessors', '')
            if pd.isna(preds):
                pred_list = []
            else:
                pred_list = [p.strip() for p in str(preds).split(',') if p.strip()]

            self.add_activity(
                activity_id=str(row['activity_id']),
                name=row['name'],
                duration=int(row['duration']),
                predecessors=pred_list
            )

    def _forward_pass(self):
        """Calculate early start and early finish (forward pass)."""

        # Topological sort
        sorted_activities = self._topological_sort()

        for activity_id in sorted_activities:
            activity = self.activities[activity_id]

            # Early start = max(early finish of all predecessors)
            if not activity.predecessors:
                activity.early_start = 0
            else:
                activity.early_start = max(
                    self.activities[pred].early_finish
                    for pred in activity.predecessors
                    if pred in self.activities
                )

            activity.early_finish = activity.early_start + activity.duration

    def _backward_pass(self):
        """Calculate late start and late finish (backward pass)."""

        # Find project duration
        project_duration = max(a.early_finish for a in self.activities.values())

        # Build successors map
        successors = defaultdict(list)
        for activity_id, activity in self.activities.items():
            for pred in activity.predecessors:
                if pred in self.activities:
                    successors[pred].append(activity_id)

        # Reverse topological order
        sorted_activities = self._topological_sort()[::-1]

        for activity_id in sorted_activities:
            activity = self.activities[activity_id]

            # Late finish = min(late start of all successors)
            if activity_id not in successors or not successors[activity_id]:
                activity.late_finish = project_duration
            else:
                activity.late_finish = min(
                    self.activities[succ].late_start
                    for succ in successors[activity_id]
                )

            activity.late_start = activity.late_finish - activity.duration

            # Calculate floats
            activity.total_float = activity.late_start - activity.early_start
            activity.is_critical = activity.total_float == 0

    def _topological_sort(self) -> List[str]:
        """Topological sort of activities."""

        visited = set()
        result = []

        def visit(activity_id: str):
            if activity_id in visited:
                return
            visited.add(activity_id)

            activity = self.activities.get(activity_id)
            if activity:
                for pred in activity.predecessors:
                    if pred in self.activities:
                        visit(pred)
                result.append(activity_id)

        for activity_id in self.activities:
            visit(activity_id)

        return result

    def calculate_critical_path(self) -> CriticalPathResult:
        """Calculate critical path and all float values."""

        self._forward_pass()
        self._backward_pass()

        # Find critical path
        critical_activities = [
            a.activity_id for a in self.activities.values()
            if a.is_critical
        ]

        # Near-critical activities
        near_critical = [
            a.activity_id for a in self.activities.values()
            if 0 < a.total_float <= self.NEAR_CRITICAL_THRESHOLD
        ]

        project_duration = max(a.early_finish for a in self.activities.values())
        total_float = sum(a.total_float for a in self.activities.values())

        return CriticalPathResult(
            critical_path=critical_activities,
            project_duration=project_duration,
            activities=self.activities,
            near_critical=near_critical,
            total_float_days=total_float
        )

    def get_schedule_dates(self) -> pd.DataFrame:
        """Get schedule with dates."""

        data = []
        for activity in self.activities.values():
            early_start_date = self.project_start + timedelta(days=activity.early_start)
            early_finish_date = self.project_start + timedelta(days=activity.early_finish)
            late_start_date = self.project_start + timedelta(days=activity.late_start)
            late_finish_date = self.project_start + timedelta(days=activity.late_finish)

            data.append({
                'Activity ID': activity.activity_id,
                'Name': activity.name,
                'Duration': activity.duration,
                'Early Start': early_start_date,
                'Early Finish': early_finish_date,
                'Late Start': late_start_date,
                'Late Finish': late_finish_date,
                'Total Float': activity.total_float,
                'Critical': 'Yes' if activity.is_critical else 'No'
            })

        return pd.DataFrame(data)

    def analyze_delay_impact(self,
                             activity_id: str,
                             delay_days: int) -> Dict[str, Any]:
        """Analyze impact of delay on project."""

        activity = self.activities.get(activity_id)
        if not activity:
            return {}

        absorbed_by_float = min(delay_days, activity.total_float)
        project_delay = max(0, delay_days - activity.total_float)

        # Find affected activities
        affected = []
        if project_delay > 0:
            # Activities that could be affected (successors)
            for a in self.activities.values():
                if activity_id in a.predecessors:
                    affected.append(a.activity_id)

        return {
            'activity': activity_id,
            'delay_days': delay_days,
            'available_float': activity.total_float,
            'absorbed_by_float': absorbed_by_float,
            'project_delay': project_delay,
            'affected_activities': affected,
            'is_critical_delay': project_delay > 0
        }

    def suggest_acceleration(self,
                             target_reduction: int) -> List[Dict[str, Any]]:
        """Suggest activities to accelerate to meet target."""

        result = self.calculate_critical_path()
        suggestions = []

        # Focus on critical activities
        for activity_id in result.critical_path:
            activity = self.activities[activity_id]

            # Assume can reduce by 20% max
            max_reduction = int(activity.duration * 0.2)

            if max_reduction > 0:
                suggestions.append({
                    'activity': activity_id,
                    'name': activity.name,
                    'current_duration': activity.duration,
                    'max_reduction': max_reduction,
                    'reason': 'Critical path activity'
                })

        # Sort by potential impact
        return sorted(suggestions, key=lambda x: x['max_reduction'], reverse=True)

    def export_analysis(self, output_path: str) -> str:
        """Export analysis to Excel."""

        result = self.calculate_critical_path()

        with pd.ExcelWriter(output_path, engine='openpyxl') as writer:
            # Summary
            summary_df = pd.DataFrame([{
                'Project Start': self.project_start,
                'Project Duration': result.project_duration,
                'Project Finish': self.project_start + timedelta(days=result.project_duration),
                'Critical Activities': len(result.critical_path),
                'Near-Critical Activities': len(result.near_critical),
                'Total Float (days)': result.total_float_days
            }])
            summary_df.to_excel(writer, sheet_name='Summary', index=False)

            # Schedule
            schedule_df = self.get_schedule_dates()
            schedule_df.to_excel(writer, sheet_name='Schedule', index=False)

            # Critical Path
            critical_df = pd.DataFrame([
                {
                    'Activity': a_id,
                    'Name': self.activities[a_id].name,
                    'Duration': self.activities[a_id].duration
                }
                for a_id in result.critical_path
            ])
            critical_df.to_excel(writer, sheet_name='Critical Path', index=False)

        return output_path

Quick Start

python
from datetime import date

# Initialize analyzer
analyzer = CriticalPathAnalyzer(project_start=date(2024, 6, 1))

# Add activities
analyzer.add_activity("A", "Site Preparation", 10, [])
analyzer.add_activity("B", "Foundation Excavation", 15, ["A"])
analyzer.add_activity("C", "Foundation Concrete", 20, ["B"])
analyzer.add_activity("D", "Structural Steel", 30, ["C"])
analyzer.add_activity("E", "MEP Rough-in", 25, ["C"])
analyzer.add_activity("F", "Exterior Walls", 20, ["D"])
analyzer.add_activity("G", "Interior Finish", 15, ["E", "F"])

# Calculate critical path
result = analyzer.calculate_critical_path()

print(f"Project Duration: {result.project_duration} days")
print(f"Critical Path: {result.critical_path}")

Common Use Cases

1. Analyze Delay Impact

python
impact = analyzer.analyze_delay_impact("C", delay_days=5)
print(f"Project Delay: {impact['project_delay']} days")

2. Get Schedule Dates

python
schedule = analyzer.get_schedule_dates()
print(schedule[['Activity ID', 'Early Start', 'Late Finish', 'Total Float']])

3. Acceleration Suggestions

python
suggestions = analyzer.suggest_acceleration(target_reduction=10)
for s in suggestions:
    print(f"{s['activity']}: can reduce {s['max_reduction']} days")

Resources

  • DDC Book: Chapter 4.2 - Schedule Analysis

Bundled files

The model reads these on demand while the skill is loaded. They are exposed as readable files and are never executed.

Frequently asked questions

What does the Critical Path Analyzer AI skill do?

Analyze project critical path from schedule data. Identify critical activities, calculate float, and assess schedule risk.

Why use Critical Path Analyzer on TypingMind?

Because you install it once and use it with any model. Critical Path Analyzer is plain Markdown rather than provider-specific code, so the same skill runs on GPT-5, Claude, Gemini, Grok, or a local model — and you can switch model mid-chat without it breaking. TypingMind runs on your own API keys, so you pay providers directly instead of a per-seat subscription, and your skills and chats stay in your own storage.

How do I install Critical Path Analyzer in TypingMind?

Open Plugins → Skills → Install from GitHub in TypingMind and paste https://github.com/datadrivenconstruction/DDC_Skills_for_AI_Agents_in_Construction/tree/main/1_DDC_Toolkit/Schedule-Management/critical-path-analyzer. TypingMind reads its SKILL.md and bundles its files and installs it as a skill you can enable per chat.

Which AI models can use Critical Path Analyzer?

Any model you connect in TypingMind. AI skills are plain Markdown instructions rather than provider-specific code, so GPT, Claude, Gemini, Grok, and local models can all load this skill when a request matches it.

How many AI models can I use with Critical Path Analyzer?

As many as you like. As long as a model supports skills, you can use Critical Path Analyzer with it — GPT, Claude, Gemini, Grok, DeepSeek, Mistral, Llama and more — all on TypingMind with your own API keys.

Is the Critical Path Analyzer AI skill free?

Yes. It is published on GitHub by datadrivenconstruction under the MIT license. You only pay your own AI provider for the tokens you use.

What are AI skills?

An AI skill is a reusable instruction bundle that teaches an AI model how to do one specific task. It follows the open Agent Skills format: a SKILL.md file with a name and description, plus any scripts, templates or reference files the model may need. The model reads the instructions only when your request matches the skill, so an installed skill costs nothing until it is used.

How are AI skills different from plugins or MCP servers?

A plugin or MCP server gives a model new tools to call — code that runs somewhere and returns a result. An AI skill gives the model knowledge and process instead: how to approach a task, which steps to follow, what good output looks like. Skills are plain Markdown, so they need no server, no API key and no runtime, and they work with any model.

View all

Set up your own AI workspace now

Get notified about new features and future giveaways by subscribing to our newsletter 👇