Skill: AL Project Estimation
Purpose
Estimate AL/Business Central projects: complexity scoring, PERT 3-point estimation, SWOT/DAFO risk analysis, cost breakdown by phase, resource allocation, and structured presales documentation.
When to Load
This skill should be loaded when:
- A new BC/AL project needs time and cost estimation
- A feasibility assessment or SWOT analysis is required before commitment
- A presales proposal or technical assessment document is being created
- Resource allocation and team composition need to be defined
- A project plan with milestones and payment schedule is needed
Core Patterns
Pattern 1: Intake Questions (Mandatory)
Before any estimation, gather these parameters:
markdown## Project Intake — Required Information ### 1. Project Identity - Project name (will be used for folder structure) - Brief description: What problem does it solve? ### 2. Cost Parameters (MANDATORY) - Hourly rate (e.g., €75/hour, $100/hour) - Currency (EUR, USD, GBP) - Contingency buffer: Yes/No (default 15-20%) - Risk buffer: Low (10%), Medium (20%), High (30%) ### 3. Technical Context - Target BC version: SaaS, On-Premise, or both? - Target delivery date - Existing codebase? (repository URL or workspace path) - Reference repositories for similar functionality? ### 4. Team (optional) - Available developers: Junior, Mid, Senior? - BC experience level: New, Experienced, Expert?
PAUSE — do NOT proceed without cost parameters. Estimation without rates is meaningless.
Pattern 2: Complexity Scoring
Score each dimension 1-10 to derive overall project complexity:
markdown## Complexity Assessment | Dimension | Score (1-10) | Criteria | |---|---|---| | Data Model | /10 | Tables, relations, migration needs | | Business Logic | /10 | Codeunits, validations, calculations | | UI Complexity | /10 | Pages, customizations, RoleCenter | | Integrations | /10 | External APIs, events, webhooks | | Reporting | /10 | Reports, queries, analytics | | Security | /10 | Permissions, data sensitivity, audit | | Testing | /10 | Test coverage needed, edge cases | | Migration/Upgrade | /10 | Data migration, version compatibility | **Overall Complexity**: (sum / 80) × 10 = X/10
Object count estimation:
| Object Type | Low Complexity | Medium | High |
|---|---|---|---|
| Table | 2-4 hrs | 4-8 hrs | 8-16 hrs |
| Page (Card/List) | 2-4 hrs | 4-8 hrs | 8-16 hrs |
| Page (Document) | 4-8 hrs | 8-16 hrs | 16-32 hrs |
| Codeunit | 2-8 hrs | 8-16 hrs | 16-40 hrs |
| Report | 4-8 hrs | 8-16 hrs | 16-32 hrs |
| Integration | 8-16 hrs | 16-32 hrs | 32-80 hrs |
Pattern 3: PERT 3-Point Estimation
Use the Program Evaluation and Review Technique for each task:
markdown## PERT Formula E = (O + 4M + P) / 6 Where: - O = Optimistic (best case, everything goes right) - M = Most Likely (normal case, typical obstacles) - P = Pessimistic (worst case, major obstacles) - E = Expected duration
Apply per development phase:
markdown## Phase Breakdown ### Phase 1: Analysis & Design | Task | O (hrs) | M (hrs) | P (hrs) | E (hrs) | |---|---|---|---|---| | Requirements analysis | 8 | 16 | 24 | 16 | | Technical design | 8 | 12 | 20 | 13 | | Architecture review | 4 | 8 | 12 | 8 | | **Subtotal** | **20** | **36** | **56** | **37** | ### Phase 2: Development | Task | O (hrs) | M (hrs) | P (hrs) | E (hrs) | |---|---|---|---|---| | Tables & data model | X | X | X | X | | Pages & UI | X | X | X | X | | Business logic | X | X | X | X | | Integrations | X | X | X | X | | **Subtotal** | **X** | **X** | **X** | **X** | ### Phase 3: Testing & QA | Task | O (hrs) | M (hrs) | P (hrs) | E (hrs) | |---|---|---|---|---| | Unit tests | X | X | X | X | | Integration tests | X | X | X | X | | UAT support | X | X | X | X | | Bug fixes | X | X | X | X | | **Subtotal** | **X** | **X** | **X** | **X** | ### Phase 4: Deployment & Documentation | Task | O (hrs) | M (hrs) | P (hrs) | E (hrs) | |---|---|---|---|---| | Technical documentation | X | X | X | X | | Training materials | X | X | X | X | | Deployment | X | X | X | X | | Post-go-live support | X | X | X | X | | **Subtotal** | **X** | **X** | **X** | **X** |
Pattern 4: SWOT/DAFO Analysis
Structured risk and opportunity assessment:
markdown## SWOT Analysis ### Strengths (Internal Positive) | ID | Strength | Impact | |---|---|---| | S1 | [e.g., Team has BC experience] | High/Medium/Low | ### Opportunities (External Positive) | ID | Opportunity | Impact | |---|---|---| | O1 | [e.g., Standard BC API available] | High/Medium/Low | ### Weaknesses (Internal Negative) | ID | Weakness | Impact | Mitigation | |---|---|---|---| | W1 | [e.g., No existing test suite] | High | Implement TDD from start | ### Threats (External Negative) | ID | Threat | Probability | Impact | Mitigation | |---|---|---|---|---| | T1 | [e.g., BC version upgrade mid-project] | Medium | High | Pin BC version | ## Feasibility Score | Criterion | Score (1-10) | |---|---| | Technical Feasibility | /10 | | Resource Feasibility | /10 | | Timeline Feasibility | /10 | | Economic Feasibility | /10 | | **Overall** | **/10** | ### Recommendation - [ ] **GO** — Project viable, proceed - [ ] **CAUTION** — Viable with conditions - [ ] **NO-GO** — Not recommended currently
Pattern 5: Cost Summary and Payment Milestones
Consolidate estimation into a financial summary:
markdown## Cost Summary | Concept | Hours | Rate | Cost | |---|---|---|---| | Analysis & Design | X | [RATE] | [TOTAL] | | Development | X | [RATE] | [TOTAL] | | Testing & QA | X | [RATE] | [TOTAL] | | Deployment & Docs | X | [RATE] | [TOTAL] | | **Subtotal** | **X** | | **[TOTAL]** | | Contingency ([%]%) | X | | [TOTAL] | | Risk Buffer ([%]%) | X | | [TOTAL] | | **TOTAL** | **X** | | **[CURRENCY] [TOTAL]** | ## Payment Milestones | Milestone | % | Amount | Deliverable | |---|---|---|---| | Project Start | 20% | [X] | SOW signed, project plan | | Design Approved | 20% | [X] | Architecture approved | | Development Complete | 30% | [X] | Code delivered, tests pass | | UAT Approved | 20% | [X] | User acceptance sign-off | | Go-Live | 10% | [X] | Production deployment |
Workflow
Step 1: Intake
- Ask mandatory intake questions (Pattern 1)
- Confirm cost parameters — do NOT skip this
- If reference repositories provided, analyze them for scope comparison
Step 2: Analyze
- Score complexity dimensions (Pattern 2)
- Count estimated objects (tables, pages, codeunits, reports)
- Identify integration points and external dependencies
- If existing codebase, use
al_search_objectsto measure current scope
Step 3: Estimate
- Apply PERT 3-point estimation per phase (Pattern 3)
- Use complexity-based hour ranges for object estimation
- Apply standard ratios:
- Testing = 30-40% of development
- Documentation = 10-15% of total
- Integration = typically underestimated by 50% — adjust accordingly
- Data migration = 15-20% of total (if applicable)
- BC version testing = 5-10% for compatibility
Step 4: Risk Assessment
- Conduct SWOT analysis (Pattern 4)
- Calculate feasibility score
- Provide clear GO / CAUTION / NO-GO recommendation
Step 5: Deliver Proposal
- Create cost summary with payment milestones (Pattern 5)
- Define resource allocation (roles, FTE, duration)
- Compile all sections into presales documentation
- Store in
Technical_PreSales/{project-slug}/folder structure
PAUSE — present proposal for stakeholder review before commitment.
Estimation Guidelines
| Rule | Guideline |
|---|---|
| Testing effort | Always 30-40% of development hours |
| Documentation | Never skip — 10-15% of total hours |
| Integration complexity | Usually underestimated — add 50% buffer |
| Data migration | Add if mentioned — 15-20% of total |
| BC version testing | Add 5-10% for compatibility verification |
| Training | 8-16 hours per user group |
| Contingency | 15-20% standard, 25-30% for high uncertainty |
References
- PERT Estimation Technique
- BC Extension Development Guide
- AppSource Submission Requirements
- BC Licensing Model
Constraints
- This skill covers project estimation, risk analysis, and presales documentation
- Do NOT estimate without cost parameters (hourly rate, currency) — ask first
- Do NOT build, compile, or deploy code — estimation only
- Do NOT modify production source code — analysis and documentation only
- Do NOT skip the SWOT analysis for any project — risk awareness is mandatory
- Architecture design → al-architect agent | Technical specifications → al-spec.create workflow | Implementation → al-conductor agent