Agile Project Management

Community
Omar-Obando
agile-project-management

Use when managing agile projects, facilitating Scrum ceremonies, conducting backlog grooming, sprint planning, velocity tracking, and implementing Kanban workflows. Includes agile metrics, team dynamics, and agile transformation guidance. Based on CSM, CSP, PRINCE2 certifications.

Overview

PublisherOmar-Obando
Repositoryqwen-orchestrator
Skill nameagile-project-management
Stars
53
Forks
13
Bundled files
Instructions only
LicenseMIT
Links
  • Markdown instructions

    A SKILL.md file the model loads on demand, so it only costs tokens when a request actually matches.

  • Works with any LLM

    AI skills are plain Markdown, not provider-specific code, so this works with GPT, Claude, Gemini, Grok, or a local model.

  • Self-contained

    Everything the model needs lives in the instructions — no extra files to sync.

  • Open source

    Published by Omar-Obando on GitHub. Read the source before you install it.

Installation

Install the Agile Project Management AI skill in TypingMind to use it with any LLM, or drop it into another agent that reads SKILL.md.

1

Install in TypingMind

TypingMind installs a skill straight from its GitHub folder — it reads SKILL.md, bundles the resource files, and stores the result locally.

  1. Open the app and go to Plugins → Skills.
  2. Choose "Install from GitHub".
  3. Paste the skill folder URL below and confirm.
    https://github.com/Omar-Obando/qwen-orchestrator/tree/main/skills/agile-project-management
  4. Enable the skill in any chat where you want it available.
Plugins → Skills → Add skill → From GitHub URL, then paste the folder URL and press Continue.
2

Install in another agent

Any agent that reads the Agent Skills format can use this skill — copy the folder into that agent's skills directory.

Claude Code — .claude/skills
git clone --depth 1 https://github.com/Omar-Obando/qwen-orchestrator.git /tmp/qwen-orchestrator
mkdir -p .claude/skills
cp -r /tmp/qwen-orchestrator/skills/agile-project-management .claude/skills/agile-project-management
Restart Claude Code after copying so it picks up the new skill.

Use it in TypingMind

Enable Agile Project Management in any TypingMind chat and the model takes it from there. Its name and description sit in the system prompt, and the moment a request matches, the model loads the full instructions itself — you never invoke it by hand, and it costs no tokens until it is actually used.

The model loads Agile Project Management on its own as soon as a request matches it.

Works with any AI model

AI skills are plain Markdown instructions rather than provider-specific code, so Agile Project Management is not tied to the model it was written for. Install it once in TypingMind and use it with GPT-5, Claude, Gemini, Grok, DeepSeek, Mistral, Llama, or a local model you run yourself — all on your own API keys.

  • Loaded only when it is needed

    The system prompt carries just the name and description. The instructions are fetched on the first matching request, so an idle skill costs nothing.

  • Switch models mid-chat

    Because the skill is instructions rather than code, changing model does not break it — the next model reads the same SKILL.md.

Skill instructions

This is the SKILL.md content the model loads. Read it before installing — a skill is instructions your model will follow.

Agile Project Management Skill — Project Manager

Overview

This skill provides comprehensive guidance for managing agile projects following Scrum, Kanban, and hybrid methodologies. It covers Scrum ceremonies, backlog grooming, sprint planning, velocity tracking, and agile metrics following CSM, CSP, and PRINCE2 certifications.

When to Use

Use this skill when:

  • Managing agile projects using Scrum
  • Facilitating Scrum ceremonies (standups, planning, reviews, retrospectives)
  • Conducting backlog grooming and refinement
  • Planning sprints and setting sprint goals
  • Tracking team velocity and capacity
  • Implementing Kanban workflows
  • Managing agile project metrics
  • Facilitating agile team meetings
  • Coaching teams on agile practices
  • Managing agile project documentation
  • Implementing agile project governance
  • Conducting agile project reviews
  • Managing agile project risks
  • Implementing agile project quality
  • Managing agile project scope
  • Conducting agile project estimation
  • Implementing agile project scheduling
  • Managing agile project stakeholder expectations
  • Conducting agile project reporting
  • Implementing agile project communication
  • Managing agile project dependencies
  • Conducting agile project release planning
  • Implementing agile project portfolio management

Do NOT use this skill when:

  • Writing application business logic (use domain-driven skill)
  • Designing database schemas (use database-design skill)
  • Writing API endpoint specifications (use api-design skill)
  • Performing security audits (use security-auditor skill)
  • Writing SQL queries (use sql-best-practices skill)
  • Designing multi-page website layouts (use design-system skill)
  • Analyzing deployment configurations (use deployment skill)
  • Writing documentation (use documentation-best-practices skill)

Scrum Framework

Scrum Ceremonies

┌─────────────────────────────────────────────────────────────┐
│              Scrum Ceremonies                               │
├─────────────────────────────────────────────────────────────┤
│  1. Sprint Planning (2-4 hours)                             │
│     - Set sprint goal                                       │
│     - Select backlog items                                  │
│     - Break down tasks                                      │
│                                                              │
│  2. Daily Standup (15 minutes)                              │
│     - What did you do yesterday?                            │
│     - What will you do today?                               │
│     - Any blockers?                                         │
│                                                              │
│  3. Sprint Review (1-2 hours)                               │
│     - Demo completed work                                   │
│     - Gather feedback                                       │
│     - Update backlog                                        │
│                                                              │
│  4. Sprint Retrospective (60-90 minutes)                    │
│     - What went well?                                       │
│     - What could improve?                                   │
│     - Action items                                          │
└─────────────────────────────────────────────────────────────┘

Sprint Planning Template

┌─────────────────────────────────────────────────────────────┐
│              Sprint Planning Agenda                         │
├─────────────────────────────────────────────────────────────┤
│  1. Sprint Goal Definition (15 min)                         │
│     - Clear, measurable goal                                │
│     - Align with product vision                             │
│                                                              │
│  2. Story Selection (30 min)                                │
│     - Review high-priority stories                          │
│     - Estimate effort                                       │
│     - Commit to achievable amount                           │
│                                                              │
│  3. Task Breakdown (30 min)                                 │
│     - Break stories into tasks                              │
│     - Assign task owners                                    │
│     - Identify risks                                        │
│                                                              │
│  4. Commitment & Capacity (15 min)                          │
│     - Verify team capacity                                  │
│     - Confirm sprint goal                                   │
│     - Document commitments                                  │
└─────────────────────────────────────────────────────────────┘

Backlog Management

Backlog Grooming Template

┌─────────────────────────────────────────────────────────────┐
│              Backlog Grooming Session                       │
├─────────────────────────────────────────────────────────────┤
│  Frequency: Weekly, 60-90 minutes                           │
│  Attendees: Product Owner, Tech Lead, Team                  │
│                                                              │
│  1. Review Completed Items (10 min)                         │
│     - Demo completed work                                   │
│     - Accept or reject                                      │
│                                                              │
│  2. Prioritize New Requests (20 min)                        │
│     - Review new requests                                   │
│     - Prioritize using MoSCoW                               │
│     - Assign priority                                       │
│                                                              │
│  3. Refine Upcoming Stories (30 min)                        │
│     - Break down large stories                              │
│     - Add acceptance criteria                               │
│     - Update estimates                                      │
│                                                              │
│  4. Estimate New Stories (20 min)                           │
│     - Use planning poker                                    │
│     - Resolve estimation discrepancies                      │
│     - Update story points                                   │
│                                                              │
│  5. Identify Dependencies (10 min)                          │
│     - Identify cross-team dependencies                      │
│     - Plan coordination                                     │
└─────────────────────────────────────────────────────────────┘

Backlog Prioritization

┌─────────────────────────────────────────────────────────────┐
│              Prioritization Techniques                      │
├─────────────────────────────────────────────────────────────┤
│  MoSCoW Method:                                             │
│  - Must have: Critical for MVP                              │
│  - Should have: Important but not critical                  │
│  - Could have: Nice to have                                 │
│  - Won't have: Not in current scope                         │
│                                                              │
│  Value vs Effort Matrix:                                    │
│  High Value ──┐    ●    ●                                   │
│               │  ●                                          │
│               │                                             │
│  Low Value ──└───────────────► Low Effort                   │
│                                                              │
│  RICE Scoring:                                              │
│  Score = (Reach × Impact × Confidence) / Effort             │
└─────────────────────────────────────────────────────────────┘

Velocity Tracking

Velocity Calculation

┌─────────────────────────────────────────────────────────────┐
│              Velocity Tracking                              │
├─────────────────────────────────────────────────────────────┤
│  Sprint 1: 24 points completed                              │
│  Sprint 2: 28 points completed                              │
│  Sprint 3: 22 points completed                              │
│  Sprint 4: 26 points completed                              │
│                                                              │
│  Velocity = (24 + 28 + 22 + 26) / 4 = 25 points             │
│                                                              │
│  Capacity Planning:                                         │
│  Team Capacity = Velocity × (1 - Buffer)                    │
│  Buffer = 30% (meetings, unplanned, learning)               │
│  Capacity = 25 × 0.7 = 17.5 points                          │
└─────────────────────────────────────────────────────────────┘

Velocity Chart

┌─────────────────────────────────────────────────────────────┐
│              Velocity Chart                                 │
├─────────────────────────────────────────────────────────────┤
│  30 ┤                  ●                                    │
│  28 ┤               ●    ●                                  │
│  26 ┤            ●           ●                              │
│  24 ┤         ●                                             │
│  22 ┤      ●                                                │
│     └───────────────────────────────────────               │
│       S1    S2    S3    S4    S5    S6    S7               │
│                                                              │
│  Trend: Stable velocity (22-28 points)                      │
│  Action: Continue current pace                              │
└─────────────────────────────────────────────────────────────┘

Kanban Methodology

Kanban Board

┌─────────────────────────────────────────────────────────────┐
│              Kanban Board                                   │
├─────────────────────────────────────────────────────────────┤
│  ┌───────────┐  ┌───────────┐  ┌───────────┐  ┌───────────┐│
│  │  Backlog  │  │  To Do    │  │ In Progress│  │  Done     ││
│  │  [15]     │  │  [3]      │  │  [5]      │  │  [20]     ││
│  └───────────┘  └───────────┘  └───────────┘  └───────────┘│
│         │             │             │             │          │
│         └─────────────┴─────────────┴─────────────┘          │
│                              │                               │
│                    ┌─────────▼─────────┐                     │
│                    │  WIP Limit: 5     │                     │
│                    └───────────────────┘                     │
└─────────────────────────────────────────────────────────────┘

Kanban Metrics

┌─────────────────────────────────────────────────────────────┐
│              Kanban Metrics                                 │
├─────────────────────────────────────────────────────────────┤
│  Cycle Time: Time from start to completion                  │
│  Lead Time: Time from request to completion                 │
│  Throughput: Number of items completed per time period      │
│  WIP: Work in Progress                                      │
│                                                              │
│  Example:                                                   │
│  - Average Cycle Time: 3 days                               │
│  - Average Lead Time: 5 days                                │
│  - Weekly Throughput: 8 items                               │
│  - Current WIP: 5 (limit: 5)                                │
└─────────────────────────────────────────────────────────────┘

Agile Metrics

burndown Chart

┌─────────────────────────────────────────────────────────────┐
│              Burndown Chart                                 │
├─────────────────────────────────────────────────────────────┤
│  Stories Remaining                                          │
│  20 ┤    ╱                                                  │
│  15 ┤   ╱                                                   │
│  10 ┤  ╱                                                    │
│   5 ┤ ╱                                                     │
│   0 └───────────────────────────────────────               │
│     Day 1  Day 5  Day 10  Day 15  Day 20                   │
│                                                              │
│  Trend: On track (blue line)                                │
│  Action: Continue current pace                              │
└─────────────────────────────────────────────────────────────┘

Agile Dashboard

┌─────────────────────────────────────────────────────────────┐
│              Agile Dashboard                                │
├─────────────────────────────────────────────────────────────┤
│  ┌─────────────┐  ┌─────────────┐  ┌─────────────┐         │
│  │  Velocity   │  │  Sprint     │  │  Burnup     │         │
│  │  Chart      │  │  Progress   │  │  Chart      │         │
│  └─────────────┘  └─────────────┘  └─────────────┘         │
│  ┌─────────────┐  ┌─────────────┐  ┌─────────────┐         │
│  │  Blockers   │  │  Team       │  │  Quality    │         │
│  │  List       │  │  Capacity   │  │  Metrics    │         │
│  └─────────────┘  └─────────────┘  └─────────────┘         │
└─────────────────────────────────────────────────────────────┘

Real-World Impact

Before this skill:

  • Unstructured project management
  • Missed deadlines
  • Scope creep
  • Team confusion
  • No visibility

After this skill:

  • Structured agile project management
  • On-time delivery
  • Clear scope and priorities
  • Team alignment
  • Transparent progress

Cross-References

  • product-owner - For backlog management and user stories
  • scrum-master - For facilitating Agile ceremonies
  • devops-pipeline - For CI/CD and deployment strategies

References

Frequently asked questions

What does the Agile Project Management AI skill do?

Use when managing agile projects, facilitating Scrum ceremonies, conducting backlog grooming, sprint planning, velocity tracking, and implementing Kanban workflows. Includes agile metrics, team dynamics, and agile transformation guidance. Based on CSM, CSP, PRINCE2 certifications.

Why use Agile Project Management on TypingMind?

Because you install it once and use it with any model. Agile Project Management is plain Markdown rather than provider-specific code, so the same skill runs on GPT-5, Claude, Gemini, Grok, or a local model — and you can switch model mid-chat without it breaking. TypingMind runs on your own API keys, so you pay providers directly instead of a per-seat subscription, and your skills and chats stay in your own storage.

How do I install Agile Project Management in TypingMind?

Open Plugins → Skills → Install from GitHub in TypingMind and paste https://github.com/Omar-Obando/qwen-orchestrator/tree/main/skills/agile-project-management. TypingMind reads its SKILL.md and installs it as a skill you can enable per chat.

Which AI models can use Agile Project Management?

Any model you connect in TypingMind. AI skills are plain Markdown instructions rather than provider-specific code, so GPT, Claude, Gemini, Grok, and local models can all load this skill when a request matches it.

How many AI models can I use with Agile Project Management?

As many as you like. As long as a model supports skills, you can use Agile Project Management with it — GPT, Claude, Gemini, Grok, DeepSeek, Mistral, Llama and more — all on TypingMind with your own API keys.

Is the Agile Project Management AI skill free?

Yes. It is published on GitHub by Omar-Obando under the MIT license. You only pay your own AI provider for the tokens you use.

What are AI skills?

An AI skill is a reusable instruction bundle that teaches an AI model how to do one specific task. It follows the open Agent Skills format: a SKILL.md file with a name and description, plus any scripts, templates or reference files the model may need. The model reads the instructions only when your request matches the skill, so an installed skill costs nothing until it is used.

How are AI skills different from plugins or MCP servers?

A plugin or MCP server gives a model new tools to call — code that runs somewhere and returns a result. An AI skill gives the model knowledge and process instead: how to approach a task, which steps to follow, what good output looks like. Skills are plain Markdown, so they need no server, no API key and no runtime, and they work with any model.