Build and maintain a project Risk Register per PMBOK 8 Risk Performance Domain. Identify risks, assess probability and impact, define response strategies, and track residual risk. Use throughout the project lifecycle — not just at planning. Do not use for operational incident response or security vulnerability scanning.

Présentation

Éditeurhoavdc
DépôtCodexKit
Nom de la compétencecodexkit-risk-register
Étoiles
27
Forks
12
Fichiers inclus
1
LicenceMIT
Liens
  • Instructions en Markdown

    Un fichier SKILL.md que le modèle charge à la demande : il ne consomme donc des tokens que lorsqu’une demande correspond réellement à la compétence.

  • Compatible avec tous les LLM

    Les compétences IA sont en simple Markdown, et non en code propre à un fournisseur. Elles fonctionnent donc avec GPT, Claude, Gemini, Grok ou un modèle local.

  • 1 fichiers inclus

    Des scripts, des modèles de documents et des références que le modèle peut consulter pendant son travail. Les fichiers sont en lecture seule et ne sont jamais exécutés.

  • Open source

    Publiée par hoavdc sur GitHub. Consultez les sources avant de l’installer.

Installation

Installez la compétence IA Codexkit Risk Register dans TypingMind pour l’utiliser avec n’importe quel LLM, ou ajoutez-la à un autre agent capable de lire SKILL.md.

1

Installer dans TypingMind

TypingMind installe une compétence directement depuis son dossier GitHub : l’application lit SKILL.md, regroupe les fichiers de ressources et enregistre le tout localement.

  1. Ouvrez l’application et accédez à Plugins → Compétences.
  2. Choisissez « Installer depuis GitHub ».
  3. Collez l’URL du dossier de la compétence indiquée ci-dessous, puis confirmez.
    https://github.com/hoavdc/CodexKit/tree/main/skills/codexkit-risk-register
  4. Activez la compétence dans chaque discussion où vous souhaitez pouvoir l’utiliser.
Plugins → Compétences → Ajouter → Via URL GitHub, puis collez l’URL du dossier et appuyez sur Continuer.
2

Installer dans un autre agent

Tout agent capable de lire le format Agent Skills peut utiliser cette compétence : copiez le dossier dans le répertoire des compétences de cet agent.

Claude Code — .claude/skills
git clone --depth 1 https://github.com/hoavdc/CodexKit.git /tmp/CodexKit
mkdir -p .claude/skills
cp -r /tmp/CodexKit/skills/codexkit-risk-register .claude/skills/codexkit-risk-register
Redémarrez Claude Code après la copie pour que la nouvelle compétence soit prise en compte.

Utilisez cette compétence dans TypingMind

Activez Codexkit Risk Register dans n’importe quelle discussion TypingMind et le modèle s’occupe du reste. Le nom et la description de la compétence figurent dans le prompt système. Dès qu’une demande correspond, le modèle charge lui-même l’intégralité des instructions : vous n’avez jamais à l’invoquer manuellement, et elle ne consomme aucun token tant qu’elle n’est pas utilisée.

Le modèle charge automatiquement Codexkit Risk Register dès qu’une demande correspond à cette compétence.

Compatible avec tous les modèles IA

Les compétences IA sont de simples instructions Markdown, et non du code propre à un fournisseur. Ainsi, Codexkit Risk Register n’est pas lié au modèle pour lequel cette compétence a été conçue. Installez-la une seule fois dans TypingMind et utilisez-la avec GPT-5, Claude, Gemini, Grok, DeepSeek, Mistral, Llama ou un modèle local que vous exécutez vous-même, le tout avec vos propres clés API.

  • Chargée uniquement en cas de besoin

    Le prompt système ne contient que le nom et la description. Les instructions sont récupérées à la première demande correspondante : une compétence inutilisée ne coûte donc rien.

  • Changez de modèle en cours de discussion

    La compétence étant constituée d’instructions et non de code, elle reste fonctionnelle lorsque vous changez de modèle : le nouveau modèle lit le même fichier SKILL.md.

Instructions de la compétence

Voici le contenu de SKILL.md que le modèle charge. Lisez-le avant l’installation : une compétence contient des instructions que votre modèle suivra.

Risk Register Manager

Purpose

Systematically identify, assess, and manage project risks using a structured register with probability/impact scoring and defined response strategies.

When to use

  • project kick-off to establish the initial risk baseline
  • sprint or milestone reviews to update and add emerging risks
  • before major decisions to assess risk exposure
  • when stakeholders request a risk assessment report

When not to use

  • live incident response or post-mortem analysis
  • security vulnerability scanning (use security tools)
  • personal task risk assessment

Inputs

  • project scope, objectives, and constraints
  • project type (predictive / adaptive / hybrid)
  • stakeholder list and their risk tolerance
  • known assumptions and dependencies
  • lessons learned from similar projects (if available)

Procedure

  1. Identify risks using multiple sources:
    • Internal: technical complexity, resource gaps, schedule pressure, budget
    • External: market shifts, regulatory changes, vendor reliability, geopolitical
    • PMBOK 8 emphasis: sustainability risks (ESG, climate, social impact)
    • Techniques: brainstorming, PESTLE analysis, Risk Breakdown Structure (RBS)
  2. Assess each risk qualitatively:
    • Probability: Very Low (0.1) / Low (0.3) / Medium (0.5) / High (0.7) / Very High (0.9)
    • Impact: Very Low (0.05) / Low (0.1) / Medium (0.2) / High (0.4) / Very High (0.8)
    • Risk Score = Probability × Impact
    • Red zone (≥ 0.25): immediate response required
    • Yellow zone: response plan needed
    • Green zone: monitor only
  3. Define response strategy:
    • For threats: Avoid / Transfer / Mitigate / Accept (active or passive)
    • For opportunities: Exploit / Share / Enhance / Accept
  4. Assign ownership — every risk has one named owner.
  5. Track residual risk — after response, re-score to verify reduction.
  6. SAFe integration — for SAFe teams, use ROAM board:
    • R = Resolved | O = Owned | A = Accepted | M = Mitigated

Output

  • risk register table: ID | Category | Description | Trigger | Probability | Impact | Score | Owner | Response Strategy | Residual Risk | Status
  • risk heat map summary (red/yellow/green distribution)
  • top 10 risks with detailed response plans
  • escalation list for sponsor or steering committee
  • risk trend over time (risk burn-down if tracked across sprints)

Definition of done

  • every identified risk has a probability, impact, and score
  • every red/yellow risk has a named owner and defined response strategy
  • residual risk is assessed for all mitigated risks
  • register is reviewable by stakeholders

Examples

  • "Build an initial risk register for a 6-month ERP migration project."
  • "Update the risk register after Sprint 5 — add 3 new risks we discovered."
  • "We have 15 risks but no response plans. Help me define strategies for the top 10."

Quality Criteria

  • All dependencies and prerequisites are documented
  • Changes are reversible or include a rollback plan
  • Security implications are assessed for each configuration change
  • Monitoring and alerting are defined for post-deployment validation

Verification (4C)

CheckQuestion
CorrectnessAre all configurations, permissions, and dependencies accurate?
CompletenessDoes the setup cover dev, staging, and prod environments as needed?
Context-fitIs the solution proportional to the problem (not over/under-engineered)?
ConsequenceIf deployed as-is to production, what is the highest-risk failure mode?

Edge Cases

  • Target environment has pre-existing configuration — Scan for conflicts before applying changes. Document what to preserve.
  • Permissions differ between environments — Test in staging first. Document the minimum permissions required.
  • Third-party service is unavailable or deprecated — Document fallback or alternative. Include health-check endpoints.

Changelog

  • v1.0.0 — Initial release

Fichiers inclus

Le modèle lit ces fichiers à la demande lorsque la compétence est chargée. Ils sont accessibles en lecture et ne sont jamais exécutés.

Foire aux questions

À quoi sert la compétence IA Codexkit Risk Register ?

Build and maintain a project Risk Register per PMBOK 8 Risk Performance Domain. Identify risks, assess probability and impact, define response strategies, and track residual risk. Use throughout the project lifecycle — not just at planning. Do not use for operational incident response or security vulnerability scanning.

Pourquoi utiliser Codexkit Risk Register sur TypingMind ?

Parce que vous l’installez une seule fois pour l’utiliser avec n’importe quel modèle. Codexkit Risk Register se compose de simples instructions en Markdown plutôt que de code propre à un fournisseur. La même compétence fonctionne donc avec GPT-5, Claude, Gemini, Grok ou un modèle local, et vous pouvez changer de modèle en cours de discussion sans perturber son fonctionnement. TypingMind utilise vos propres clés API : vous payez donc directement les fournisseurs plutôt qu’un abonnement par siège, et vos compétences et discussions restent dans votre propre espace de stockage.

Comment installer Codexkit Risk Register dans TypingMind ?

Dans TypingMind, ouvrez Plugins → Compétences → Installer depuis GitHub et collez https://github.com/hoavdc/CodexKit/tree/main/skills/codexkit-risk-register. TypingMind lit le fichier SKILL.md, regroupe les fichiers associés et installe le tout sous forme de compétence que vous pouvez activer pour chaque discussion.

Quels modèles d’IA peuvent utiliser Codexkit Risk Register ?

N’importe quel modèle que vous connectez dans TypingMind. Les compétences IA sont de simples instructions en Markdown, et non du code propre à un fournisseur. GPT, Claude, Gemini, Grok et les modèles locaux peuvent donc tous charger cette compétence lorsqu’une demande lui correspond.

Combien de modèles d’IA puis-je utiliser avec Codexkit Risk Register ?

Autant que vous le souhaitez. Tant qu’un modèle prend en charge les compétences, vous pouvez utiliser Codexkit Risk Register avec lui : GPT, Claude, Gemini, Grok, DeepSeek, Mistral, Llama et bien d’autres, le tout dans TypingMind avec vos propres clés API.

La compétence IA Codexkit Risk Register est-elle gratuite ?

Oui. Cette compétence est publiée sur GitHub par hoavdc sous licence MIT. Vous ne payez que votre propre fournisseur d’IA pour les tokens utilisés.

Que sont les compétences IA ?

Une compétence IA est un ensemble d’instructions réutilisables qui apprend à un modèle d’IA à accomplir une tâche précise. Elle suit le format ouvert Agent Skills : un fichier SKILL.md contenant un nom et une description, ainsi que les éventuels scripts, modèles de documents ou fichiers de référence dont le modèle peut avoir besoin. Le modèle ne lit les instructions que lorsque votre demande correspond à la compétence. Une compétence installée ne coûte donc rien tant qu’elle n’est pas utilisée.

En quoi les compétences IA diffèrent-elles des plugins ou des serveurs MCP ?

Un plugin ou un serveur MCP fournit au modèle de nouveaux outils à appeler : du code qui s’exécute quelque part et renvoie un résultat. Une compétence IA lui apporte plutôt des connaissances et une méthode : comment aborder une tâche, quelles étapes suivre et à quoi ressemble un bon résultat. Les compétences sont de simples instructions en Markdown. Elles ne nécessitent donc ni serveur, ni clé API, ni environnement d’exécution, et fonctionnent avec n’importe quel modèle.

Tout voir

Créez votre propre espace IA dès maintenant

Abonnez-vous à notre newsletter pour être informé des nouvelles fonctionnalités et des prochains cadeaux à gagner 👇