Logo di Codexkit Risk Register

Codexkit Risk Register

Community
hoavdc
codexkit-risk-register

Build and maintain a project Risk Register per PMBOK 8 Risk Performance Domain. Identify risks, assess probability and impact, define response strategies, and track residual risk. Use throughout the project lifecycle — not just at planning. Do not use for operational incident response or security vulnerability scanning.

Panoramica

Autorehoavdc
RepositoryCodexKit
Nome della skillcodexkit-risk-register
Stelle
27
Fork
12
File inclusi
1
LicenzaMIT
Link
  • Istruzioni in Markdown

    Un file SKILL.md che il modello carica quando serve, consumando token solo quando una richiesta è effettivamente pertinente.

  • Funziona con qualsiasi LLM

    Le skill IA sono in semplice Markdown, non in codice specifico di un fornitore, quindi funzionano con GPT, Claude, Gemini, Grok o un modello locale.

  • 1 file inclusi

    Script, modelli di documento e riferimenti che il modello può leggere mentre lavora. I file sono di sola lettura e non vengono mai eseguiti.

  • Open source

    Pubblicata da hoavdc su GitHub. Leggi i sorgenti prima di installarla.

Installazione

Installa la skill IA Codexkit Risk Register in TypingMind per usarla con qualsiasi LLM, oppure copiala in un altro agente in grado di leggere SKILL.md.

1

Installa in TypingMind

TypingMind installa una skill direttamente dalla sua cartella GitHub: legge SKILL.md, raccoglie i file delle risorse e salva il risultato in locale.

  1. Apri l'app e vai su Plugin → Skill.
  2. Scegli "Installa da GitHub".
  3. Incolla l'URL della cartella della skill riportato qui sotto e conferma.
    https://github.com/hoavdc/CodexKit/tree/main/skills/codexkit-risk-register
  4. Attiva la skill in ogni chat in cui vuoi averla a disposizione.
Plugin → Skill → Nuova skill → Da URL GitHub, poi incolla l'URL della cartella e premi Continua.
2

Installa in un altro agente

Qualsiasi agente che legge il formato Agent Skills può usare questa skill: copia la cartella nella cartella delle skill di quell'agente.

Claude Code — .claude/skills
git clone --depth 1 https://github.com/hoavdc/CodexKit.git /tmp/CodexKit
mkdir -p .claude/skills
cp -r /tmp/CodexKit/skills/codexkit-risk-register .claude/skills/codexkit-risk-register
Dopo la copia, riavvia Claude Code per caricare la nuova skill.

Usala in TypingMind

Attiva Codexkit Risk Register in qualsiasi chat di TypingMind e al resto pensa il modello. Il nome e la descrizione della skill sono nel prompt di sistema e, non appena arriva una richiesta pertinente, il modello carica da solo le istruzioni complete: non devi mai richiamarla manualmente e non consuma token finché non viene effettivamente usata.

Il modello carica automaticamente Codexkit Risk Register non appena riceve una richiesta pertinente.

Funziona con qualsiasi modello IA

Le skill IA sono semplici istruzioni in Markdown, non codice specifico di un fornitore, quindi Codexkit Risk Register non è vincolata al modello per cui è stata scritta. Installala una sola volta in TypingMind e usala con GPT-5, Claude, Gemini, Grok, DeepSeek, Mistral, Llama o un modello locale che esegui tu, sempre con le tue chiavi API.

  • Caricata solo quando serve

    Il prompt di sistema contiene solo il nome e la descrizione. Le istruzioni vengono recuperate alla prima richiesta pertinente, quindi una skill inutilizzata non costa nulla.

  • Cambia modello durante la chat

    Poiché la skill è composta da istruzioni e non da codice, continua a funzionare anche se cambi modello: il nuovo modello legge lo stesso file SKILL.md.

Istruzioni della skill

Questo è il contenuto di SKILL.md che il modello carica. Leggilo prima dell'installazione: una skill è un insieme di istruzioni che il tuo modello seguirà.

Risk Register Manager

Purpose

Systematically identify, assess, and manage project risks using a structured register with probability/impact scoring and defined response strategies.

When to use

  • project kick-off to establish the initial risk baseline
  • sprint or milestone reviews to update and add emerging risks
  • before major decisions to assess risk exposure
  • when stakeholders request a risk assessment report

When not to use

  • live incident response or post-mortem analysis
  • security vulnerability scanning (use security tools)
  • personal task risk assessment

Inputs

  • project scope, objectives, and constraints
  • project type (predictive / adaptive / hybrid)
  • stakeholder list and their risk tolerance
  • known assumptions and dependencies
  • lessons learned from similar projects (if available)

Procedure

  1. Identify risks using multiple sources:
    • Internal: technical complexity, resource gaps, schedule pressure, budget
    • External: market shifts, regulatory changes, vendor reliability, geopolitical
    • PMBOK 8 emphasis: sustainability risks (ESG, climate, social impact)
    • Techniques: brainstorming, PESTLE analysis, Risk Breakdown Structure (RBS)
  2. Assess each risk qualitatively:
    • Probability: Very Low (0.1) / Low (0.3) / Medium (0.5) / High (0.7) / Very High (0.9)
    • Impact: Very Low (0.05) / Low (0.1) / Medium (0.2) / High (0.4) / Very High (0.8)
    • Risk Score = Probability × Impact
    • Red zone (≥ 0.25): immediate response required
    • Yellow zone: response plan needed
    • Green zone: monitor only
  3. Define response strategy:
    • For threats: Avoid / Transfer / Mitigate / Accept (active or passive)
    • For opportunities: Exploit / Share / Enhance / Accept
  4. Assign ownership — every risk has one named owner.
  5. Track residual risk — after response, re-score to verify reduction.
  6. SAFe integration — for SAFe teams, use ROAM board:
    • R = Resolved | O = Owned | A = Accepted | M = Mitigated

Output

  • risk register table: ID | Category | Description | Trigger | Probability | Impact | Score | Owner | Response Strategy | Residual Risk | Status
  • risk heat map summary (red/yellow/green distribution)
  • top 10 risks with detailed response plans
  • escalation list for sponsor or steering committee
  • risk trend over time (risk burn-down if tracked across sprints)

Definition of done

  • every identified risk has a probability, impact, and score
  • every red/yellow risk has a named owner and defined response strategy
  • residual risk is assessed for all mitigated risks
  • register is reviewable by stakeholders

Examples

  • "Build an initial risk register for a 6-month ERP migration project."
  • "Update the risk register after Sprint 5 — add 3 new risks we discovered."
  • "We have 15 risks but no response plans. Help me define strategies for the top 10."

Quality Criteria

  • All dependencies and prerequisites are documented
  • Changes are reversible or include a rollback plan
  • Security implications are assessed for each configuration change
  • Monitoring and alerting are defined for post-deployment validation

Verification (4C)

CheckQuestion
CorrectnessAre all configurations, permissions, and dependencies accurate?
CompletenessDoes the setup cover dev, staging, and prod environments as needed?
Context-fitIs the solution proportional to the problem (not over/under-engineered)?
ConsequenceIf deployed as-is to production, what is the highest-risk failure mode?

Edge Cases

  • Target environment has pre-existing configuration — Scan for conflicts before applying changes. Document what to preserve.
  • Permissions differ between environments — Test in staging first. Document the minimum permissions required.
  • Third-party service is unavailable or deprecated — Document fallback or alternative. Include health-check endpoints.

Changelog

  • v1.0.0 — Initial release

File inclusi

Il modello legge questi file quando servono, mentre la skill è caricata. Sono accessibili in sola lettura e non vengono mai eseguiti.

Domande frequenti

Cosa fa la skill IA Codexkit Risk Register?

Build and maintain a project Risk Register per PMBOK 8 Risk Performance Domain. Identify risks, assess probability and impact, define response strategies, and track residual risk. Use throughout the project lifecycle — not just at planning. Do not use for operational incident response or security vulnerability scanning.

Perché usare Codexkit Risk Register su TypingMind?

Perché la installi una volta e la usi con qualsiasi modello. Codexkit Risk Register è scritta in semplice Markdown anziché in codice specifico di un fornitore, quindi la stessa skill funziona con GPT-5, Claude, Gemini, Grok o un modello locale, e puoi cambiare modello durante la chat senza che smetta di funzionare. TypingMind usa le tue chiavi API, quindi paghi direttamente i fornitori anziché un abbonamento per posto utente, e le tue skill e chat restano nel tuo spazio di archiviazione.

Come installo Codexkit Risk Register in TypingMind?

Apri Plugin → Skill → Installa da GitHub in TypingMind e incolla https://github.com/hoavdc/CodexKit/tree/main/skills/codexkit-risk-register. TypingMind legge il file SKILL.md, include i file associati e installa la skill, che puoi abilitare per ogni singola chat.

Quali modelli IA possono usare Codexkit Risk Register?

Qualsiasi modello che colleghi in TypingMind. Le skill IA sono semplici istruzioni in Markdown anziché codice specifico di un fornitore, quindi GPT, Claude, Gemini, Grok e i modelli locali possono tutti caricare questa skill quando una richiesta corrisponde al suo scopo.

Quanti modelli IA posso usare con Codexkit Risk Register?

Quanti ne vuoi. Se un modello supporta le skill, puoi usarlo con Codexkit Risk Register: GPT, Claude, Gemini, Grok, DeepSeek, Mistral, Llama e molti altri, tutti su TypingMind con le tue chiavi API.

La skill IA Codexkit Risk Register è gratuita?

Sì. È pubblicata su GitHub da hoavdc con licenza MIT. Paghi solo il tuo fornitore IA per i token che usi.

Cosa sono le skill IA?

Una skill IA è un pacchetto di istruzioni riutilizzabili che insegna a un modello IA come svolgere un'attività specifica. Segue il formato aperto Agent Skills: un file SKILL.md con un nome e una descrizione, più eventuali script, modelli o file di riferimento di cui il modello potrebbe aver bisogno. Il modello legge le istruzioni solo quando la tua richiesta corrisponde alla skill, quindi una skill installata non comporta costi finché non viene usata.

In cosa si differenziano le skill IA dai plugin o dai server MCP?

Un plugin o un server MCP fornisce a un modello nuovi strumenti da richiamare: codice che viene eseguito da qualche parte e restituisce un risultato. Una skill IA, invece, fornisce al modello conoscenze e procedure: come affrontare un'attività, quali passaggi seguire e quali caratteristiche deve avere un buon output. Le skill sono semplici istruzioni in Markdown, quindi non richiedono server, chiavi API né ambienti di esecuzione e funzionano con qualsiasi modello.

Vedi tutti

Crea subito la tua area di lavoro IA

Iscriviti alla nostra newsletter per ricevere aggiornamenti sulle nuove funzionalità e sulle prossime iniziative a premi 👇