Build and maintain a project Risk Register per PMBOK 8 Risk Performance Domain. Identify risks, assess probability and impact, define response strategies, and track residual risk. Use throughout the project lifecycle — not just at planning. Do not use for operational incident response or security vulnerability scanning.

Обзор

Издательhoavdc
РепозиторийCodexKit
Название навыкаcodexkit-risk-register
Звёзды
27
Форки
12
Встроенные файлы
1
ЛицензияMIT
Ссылки
  • Инструкции в формате Markdown

    Файл SKILL.md, который модель загружает по необходимости, поэтому токены расходуются только при подходящем запросе.

  • Работает с любой языковой моделью

    Навыки ИИ — это обычный Markdown, а не код для конкретного поставщика, поэтому они работают с GPT, Claude, Gemini, Grok и локальными моделями.

  • Файлы в комплекте: 1

    Скрипты, шаблоны и справочные материалы, которые модель может читать во время работы. Файлы доступны только для чтения и никогда не выполняются.

  • Открытый исходный код

    Опубликовано на GitHub: hoavdc. Перед установкой изучите исходные материалы.

Установка

Установите навык ИИ Codexkit Risk Register в TypingMind, чтобы использовать его с любой LLM, или добавьте его в другой агент, который умеет читать SKILL.md.

1

Установка в TypingMind

TypingMind устанавливает навык прямо из его папки на GitHub: читает SKILL.md, собирает файлы ресурсов и сохраняет результат локально.

  1. Откройте приложение и перейдите в раздел «Плагины → Навыки».
  2. Выберите «Установить из GitHub».
  3. Вставьте указанную ниже ссылку на папку навыка и подтвердите установку.
    https://github.com/hoavdc/CodexKit/tree/main/skills/codexkit-risk-register
  4. Включите навык в каждом чате, где хотите его использовать.
Плагины → Навыки → Новый навык → По ссылке GitHub, затем вставьте ссылку на папку и нажмите «Продолжить».
2

Установка в другом агенте

Любой агент с поддержкой формата Agent Skills может использовать этот навык — скопируйте папку в каталог навыков этого агента.

Claude Code — .claude/skills
git clone --depth 1 https://github.com/hoavdc/CodexKit.git /tmp/CodexKit
mkdir -p .claude/skills
cp -r /tmp/CodexKit/skills/codexkit-risk-register .claude/skills/codexkit-risk-register
После копирования перезапустите Claude Code, чтобы загрузить новый навык.

Использование в TypingMind

Включите навык Codexkit Risk Register в любом чате TypingMind, и дальше модель всё сделает сама. Его название и описание хранятся в системном промпте, а при появлении подходящего запроса модель сама загружает полные инструкции. Вам не нужно вызывать навык вручную, и до фактического использования он не расходует токены.

Модель сама загружает навык Codexkit Risk Register, как только появляется подходящий для него запрос.

Работает с любой моделью ИИ

Навыки ИИ — это обычные инструкции в Markdown, а не код для конкретного поставщика, поэтому навык Codexkit Risk Register не привязан к модели, для которой он был создан. Установите его один раз в TypingMind и используйте с GPT-5, Claude, Gemini, Grok, DeepSeek, Mistral, Llama или локальной моделью, которую запускаете самостоятельно, — со своими API-ключами.

  • Загружается только при необходимости

    Системный промпт содержит только название и описание. Инструкции загружаются при первом подходящем запросе, поэтому неиспользуемый навык не расходует токены.

  • Меняйте модели прямо в чате

    Навык состоит из инструкций, а не кода, поэтому смена модели не нарушает его работу: новая модель читает тот же файл SKILL.md.

Инструкции навыка

Это содержимое файла SKILL.md, которое загружает модель. Прочитайте его перед установкой: навык — это инструкции, которым будет следовать ваша модель.

Risk Register Manager

Purpose

Systematically identify, assess, and manage project risks using a structured register with probability/impact scoring and defined response strategies.

When to use

  • project kick-off to establish the initial risk baseline
  • sprint or milestone reviews to update and add emerging risks
  • before major decisions to assess risk exposure
  • when stakeholders request a risk assessment report

When not to use

  • live incident response or post-mortem analysis
  • security vulnerability scanning (use security tools)
  • personal task risk assessment

Inputs

  • project scope, objectives, and constraints
  • project type (predictive / adaptive / hybrid)
  • stakeholder list and their risk tolerance
  • known assumptions and dependencies
  • lessons learned from similar projects (if available)

Procedure

  1. Identify risks using multiple sources:
    • Internal: technical complexity, resource gaps, schedule pressure, budget
    • External: market shifts, regulatory changes, vendor reliability, geopolitical
    • PMBOK 8 emphasis: sustainability risks (ESG, climate, social impact)
    • Techniques: brainstorming, PESTLE analysis, Risk Breakdown Structure (RBS)
  2. Assess each risk qualitatively:
    • Probability: Very Low (0.1) / Low (0.3) / Medium (0.5) / High (0.7) / Very High (0.9)
    • Impact: Very Low (0.05) / Low (0.1) / Medium (0.2) / High (0.4) / Very High (0.8)
    • Risk Score = Probability × Impact
    • Red zone (≥ 0.25): immediate response required
    • Yellow zone: response plan needed
    • Green zone: monitor only
  3. Define response strategy:
    • For threats: Avoid / Transfer / Mitigate / Accept (active or passive)
    • For opportunities: Exploit / Share / Enhance / Accept
  4. Assign ownership — every risk has one named owner.
  5. Track residual risk — after response, re-score to verify reduction.
  6. SAFe integration — for SAFe teams, use ROAM board:
    • R = Resolved | O = Owned | A = Accepted | M = Mitigated

Output

  • risk register table: ID | Category | Description | Trigger | Probability | Impact | Score | Owner | Response Strategy | Residual Risk | Status
  • risk heat map summary (red/yellow/green distribution)
  • top 10 risks with detailed response plans
  • escalation list for sponsor or steering committee
  • risk trend over time (risk burn-down if tracked across sprints)

Definition of done

  • every identified risk has a probability, impact, and score
  • every red/yellow risk has a named owner and defined response strategy
  • residual risk is assessed for all mitigated risks
  • register is reviewable by stakeholders

Examples

  • "Build an initial risk register for a 6-month ERP migration project."
  • "Update the risk register after Sprint 5 — add 3 new risks we discovered."
  • "We have 15 risks but no response plans. Help me define strategies for the top 10."

Quality Criteria

  • All dependencies and prerequisites are documented
  • Changes are reversible or include a rollback plan
  • Security implications are assessed for each configuration change
  • Monitoring and alerting are defined for post-deployment validation

Verification (4C)

CheckQuestion
CorrectnessAre all configurations, permissions, and dependencies accurate?
CompletenessDoes the setup cover dev, staging, and prod environments as needed?
Context-fitIs the solution proportional to the problem (not over/under-engineered)?
ConsequenceIf deployed as-is to production, what is the highest-risk failure mode?

Edge Cases

  • Target environment has pre-existing configuration — Scan for conflicts before applying changes. Document what to preserve.
  • Permissions differ between environments — Test in staging first. Document the minimum permissions required.
  • Third-party service is unavailable or deprecated — Document fallback or alternative. Include health-check endpoints.

Changelog

  • v1.0.0 — Initial release

Встроенные файлы

Модель читает эти файлы по мере необходимости, пока навык загружен. Они доступны только для чтения и никогда не выполняются.

Часто задаваемые вопросы

Что делает навык ИИ Codexkit Risk Register?

Build and maintain a project Risk Register per PMBOK 8 Risk Performance Domain. Identify risks, assess probability and impact, define response strategies, and track residual risk. Use throughout the project lifecycle — not just at planning. Do not use for operational incident response or security vulnerability scanning.

Зачем использовать Codexkit Risk Register в TypingMind?

Потому что вы устанавливаете навык один раз и используете его с любой моделью. Codexkit Risk Register — это обычный текст в формате Markdown, а не код для конкретного поставщика, поэтому один и тот же навык работает с GPT-5, Claude, Gemini, Grok или локальной моделью. Вы можете менять модель прямо во время чата, и навык продолжит работать. TypingMind использует ваши собственные ключи API, поэтому вы платите поставщикам напрямую, а не оформляете подписку с оплатой за каждое место. Ваши навыки и чаты остаются в вашем собственном хранилище.

Как установить Codexkit Risk Register в TypingMind?

В TypingMind откройте «Плагины → Навыки → Установить из GitHub» и вставьте https://github.com/hoavdc/CodexKit/tree/main/skills/codexkit-risk-register. TypingMind прочитает файл SKILL.md, включит сопутствующие файлы в пакет и установит навык, который можно включать отдельно для каждого чата.

Какие модели ИИ могут использовать Codexkit Risk Register?

Любая модель, которую вы подключите в TypingMind. Навыки ИИ — это обычные инструкции в формате Markdown, а не код для конкретного поставщика, поэтому GPT, Claude, Gemini, Grok и локальные модели могут загружать этот навык, когда запрос ему соответствует.

Со сколькими моделями ИИ можно использовать Codexkit Risk Register?

С любым количеством. Если модель поддерживает навыки, вы можете использовать с ней Codexkit Risk Register: GPT, Claude, Gemini, Grok, DeepSeek, Mistral, Llama и другие — всё в TypingMind с вашими собственными ключами API.

Бесплатен ли навык ИИ Codexkit Risk Register?

Да. Навык опубликован на GitHub автором hoavdc по лицензии MIT. Вы платите только своему поставщику ИИ за использованные токены.

Что такое навыки ИИ?

Навык ИИ — это многоразовый набор инструкций, который объясняет модели ИИ, как выполнять конкретную задачу. Он соответствует открытому формату Agent Skills: файл SKILL.md с названием и описанием, а также любые скрипты, шаблоны или справочные файлы, которые могут понадобиться модели. Модель читает инструкции, только когда ваш запрос соответствует навыку, поэтому установленный навык ничего не стоит, пока не используется.

Чем навыки ИИ отличаются от плагинов и серверов MCP?

Плагин или сервер MCP даёт модели новые инструменты для вызова — код, который где-то выполняется и возвращает результат. Навык ИИ вместо этого даёт модели знания и порядок действий: как подойти к задаче, какие шаги выполнить и каким должен быть хороший результат. Навыки — это обычный текст в формате Markdown, поэтому им не нужны сервер, ключ API или среда выполнения, и они работают с любой моделью.

Все

Создайте свою рабочую ИИ-среду сейчас

Подпишитесь на нашу рассылку, чтобы узнавать о новых функциях и предстоящих розыгрышах 👇