Build and maintain a project Risk Register per PMBOK 8 Risk Performance Domain. Identify risks, assess probability and impact, define response strategies, and track residual risk. Use throughout the project lifecycle — not just at planning. Do not use for operational incident response or security vulnerability scanning.

Iwwersiicht

Editeurhoavdc
RepositoryCodexKit
Skill-Nummcodexkit-risk-register
Stären
27
Forks
12
Matgeliwwert Fichieren
1
LizenzMIT
Linken
  • Instruktiounen am Markdown-Format

    Eng SKILL.md-Datei, déi de Modell bei Bedarf luet, soudatt nëmmen Token ufalen, wann eng Ufro tatsächlech dozou passt.

  • Funktionéiert mat all LLM

    KI-Skills si reng Markdown, keen ubidderspezifesche Code. Dofir funktionéiert dëse Skill mat GPT, Claude, Gemini, Grok oder engem lokale Modell.

  • 1 matgeliwwert Dateien

    Skripten, Virlagen a Referenzen, déi de Modell beim Schaffe liese kann. D'Dateie kënnen nëmme gelies ginn a ginn ni ausgeféiert.

  • Open Source

    Vum hoavdc op GitHub verëffentlecht. Liest de Quelltext, ier Dir de Skill installéiert.

Installatioun

Installéiert de KI-Skill Codexkit Risk Register an TypingMind, fir e mat all LLM ze benotzen, oder füügt en an en anere KI-Agent an, deen SKILL.md liest.

1

An TypingMind installéieren

TypingMind installéiert e Skill direkt aus sengem GitHub-Dossier — dobäi gëtt SKILL.md gelies, d'Ressourcedateie gi gebëndelt an d'Resultat gëtt lokal gespäichert.

  1. Maacht d'App op a gitt op Plugins → Skills.
  2. Wielt „Vun GitHub installéieren“.
  3. Pecht d'URL vum Skill-Dossier hei drënner an a bestätegt.
    https://github.com/hoavdc/CodexKit/tree/main/skills/codexkit-risk-register
  4. Aktivéiert de Skill an all Chat, an deem Dir e benotze wëllt.
Plugins → Skills → Skill afügen → Vu GitHub-URL, pecht dann d'URL vum Dossier an a klickt op Weider.
2

An engem anere KI-Agent installéieren

All KI-Agent, deen d'Format Agent Skills liest, kann dëse Skill benotzen — kopéiert den Dossier an de Skill-Verzeechnes vun deem KI-Agent.

Claude Code — .claude/skills
git clone --depth 1 https://github.com/hoavdc/CodexKit.git /tmp/CodexKit
mkdir -p .claude/skills
cp -r /tmp/CodexKit/skills/codexkit-risk-register .claude/skills/codexkit-risk-register
Start Claude Code nom Kopéieren nei, fir datt den neie Skill erkannt gëtt.

An TypingMind benotzen

Aktivéiert Codexkit Risk Register an engem Chat vun TypingMind, an de Modell iwwerhëlt de Rescht. Den Numm an d'Beschreiwung stinn am System-Prompt. Soubal eng Ufro dozou passt, luet de Modell déi komplett Instruktioune selwer — Dir musst de Skill ni manuell opruffen, an et fale keng Token un, bis en tatsächlech benotzt gëtt.

De Modell luet Codexkit Risk Register automatesch, soubal eng Ufro dozou passt.

Funktionéiert mat all KI-Modell

KI-Skills si reng Markdown-Instruktiounen amplaz vun ubidderspezifeschem Code. Dofir ass Codexkit Risk Register net un de Modell gebonnen, fir deen de Skill geschriwwe gouf. Installéiert en eemol an TypingMind a benotzt e mat GPT-5, Claude, Gemini, Grok, DeepSeek, Mistral, Llama oder engem lokale Modell, deen Dir selwer bedreift — alles mat Ären eegenen API-Keys.

  • Gëtt nëmme gelueden, wann et néideg ass

    De System-Prompt enthält nëmmen den Numm an d'Beschreiwung. D'Instruktioune gi bei der éischter passender Ufro gelueden, soudatt en onbenotzte Skill näischt kascht.

  • De Modell am lafende Chat wiesselen

    Well de Skill aus Instruktiounen amplaz vu Code besteet, funktionéiert en och no engem Modellwiessel — den nächste Modell liest déi selwecht SKILL.md-Datei.

Skill-Instruktiounen

Dëst ass den Inhalt vu SKILL.md, deen de Modell luet. Liest e virun der Installatioun — e Skill besteet aus Instruktiounen, déi Äre Modell befollegt.

Risk Register Manager

Purpose

Systematically identify, assess, and manage project risks using a structured register with probability/impact scoring and defined response strategies.

When to use

  • project kick-off to establish the initial risk baseline
  • sprint or milestone reviews to update and add emerging risks
  • before major decisions to assess risk exposure
  • when stakeholders request a risk assessment report

When not to use

  • live incident response or post-mortem analysis
  • security vulnerability scanning (use security tools)
  • personal task risk assessment

Inputs

  • project scope, objectives, and constraints
  • project type (predictive / adaptive / hybrid)
  • stakeholder list and their risk tolerance
  • known assumptions and dependencies
  • lessons learned from similar projects (if available)

Procedure

  1. Identify risks using multiple sources:
    • Internal: technical complexity, resource gaps, schedule pressure, budget
    • External: market shifts, regulatory changes, vendor reliability, geopolitical
    • PMBOK 8 emphasis: sustainability risks (ESG, climate, social impact)
    • Techniques: brainstorming, PESTLE analysis, Risk Breakdown Structure (RBS)
  2. Assess each risk qualitatively:
    • Probability: Very Low (0.1) / Low (0.3) / Medium (0.5) / High (0.7) / Very High (0.9)
    • Impact: Very Low (0.05) / Low (0.1) / Medium (0.2) / High (0.4) / Very High (0.8)
    • Risk Score = Probability × Impact
    • Red zone (≥ 0.25): immediate response required
    • Yellow zone: response plan needed
    • Green zone: monitor only
  3. Define response strategy:
    • For threats: Avoid / Transfer / Mitigate / Accept (active or passive)
    • For opportunities: Exploit / Share / Enhance / Accept
  4. Assign ownership — every risk has one named owner.
  5. Track residual risk — after response, re-score to verify reduction.
  6. SAFe integration — for SAFe teams, use ROAM board:
    • R = Resolved | O = Owned | A = Accepted | M = Mitigated

Output

  • risk register table: ID | Category | Description | Trigger | Probability | Impact | Score | Owner | Response Strategy | Residual Risk | Status
  • risk heat map summary (red/yellow/green distribution)
  • top 10 risks with detailed response plans
  • escalation list for sponsor or steering committee
  • risk trend over time (risk burn-down if tracked across sprints)

Definition of done

  • every identified risk has a probability, impact, and score
  • every red/yellow risk has a named owner and defined response strategy
  • residual risk is assessed for all mitigated risks
  • register is reviewable by stakeholders

Examples

  • "Build an initial risk register for a 6-month ERP migration project."
  • "Update the risk register after Sprint 5 — add 3 new risks we discovered."
  • "We have 15 risks but no response plans. Help me define strategies for the top 10."

Quality Criteria

  • All dependencies and prerequisites are documented
  • Changes are reversible or include a rollback plan
  • Security implications are assessed for each configuration change
  • Monitoring and alerting are defined for post-deployment validation

Verification (4C)

CheckQuestion
CorrectnessAre all configurations, permissions, and dependencies accurate?
CompletenessDoes the setup cover dev, staging, and prod environments as needed?
Context-fitIs the solution proportional to the problem (not over/under-engineered)?
ConsequenceIf deployed as-is to production, what is the highest-risk failure mode?

Edge Cases

  • Target environment has pre-existing configuration — Scan for conflicts before applying changes. Document what to preserve.
  • Permissions differ between environments — Test in staging first. Document the minimum permissions required.
  • Third-party service is unavailable or deprecated — Document fallback or alternative. Include health-check endpoints.

Changelog

  • v1.0.0 — Initial release

Matgeliwwert Fichieren

De Modell liest dës Dateie bei Bedarf, wärend de Skill gelueden ass. Si ginn als liesbar Dateie bereetgestallt a ginn ni ausgeféiert.

Heefeg gestallte Froen

Wat mécht de KI-Skill Codexkit Risk Register?

Build and maintain a project Risk Register per PMBOK 8 Risk Performance Domain. Identify risks, assess probability and impact, define response strategies, and track residual risk. Use throughout the project lifecycle — not just at planning. Do not use for operational incident response or security vulnerability scanning.

Firwat Codexkit Risk Register op TypingMind benotzen?

Well Dir en eemol installéiert a mat all Modell benotze kënnt. Codexkit Risk Register besteet aus einfachem Markdown amplaz vun ubidderspezifeschem Code. Dee selwechte Skill funktionéiert also mat GPT-5, Claude, Gemini, Grok oder engem lokale Modell – an Dir kënnt de Modell matzen am Chat wiesselen, ouni datt de Skill ophält ze funktionéieren. TypingMind benotzt Är eegen API-Schlësselen, sou datt Dir d'Ubidder direkt bezuelt amplaz vun engem Abonnement pro Benotzerplaz. Är Skills a Chats bleiwen an Ärem eegene Späicher.

Wéi installéieren ech Codexkit Risk Register an TypingMind?

Maacht an TypingMind Plugins → Skills → Vu GitHub installéieren op a setzt https://github.com/hoavdc/CodexKit/tree/main/skills/codexkit-risk-register an. TypingMind liest d'Datei SKILL.md, bündelt déi zougehéiereg Dateien an installéiert dat Ganzt als Skill, deen Dir pro Chat aktivéiere kënnt.

Wéi eng KI-Modeller kënnen Codexkit Risk Register benotzen?

All Modell, deen Dir an TypingMind verbënnt. KI-Skills sinn einfach Markdown-Instruktiounen an net ubidderspezifesche Code. Dofir kënne GPT, Claude, Gemini, Grok a lokal Modeller dëse Skill lueden, wann eng Ufro dozou passt.

Wéi vill KI-Modeller kann ech mat Codexkit Risk Register benotzen?

Esou vill Dir wëllt. Soulaang e Modell Skills ënnerstëtzt, kënnt Dir Codexkit Risk Register domat benotzen – GPT, Claude, Gemini, Grok, DeepSeek, Mistral, Llama a méi – alles op TypingMind mat Ären eegenen API-Schlësselen.

Ass de KI-Skill Codexkit Risk Register gratis?

Jo. De Skill gëtt vum hoavdc ënner der Lizenz MIT op GitHub publizéiert. Dir bezuelt nëmmen Ären eegene KI-Ubidder fir d'Token, déi Dir benotzt.

Wat si KI-Skills?

E KI-Skill ass e weiderverwendbaart Pak vun Instruktiounen, dat engem KI-Modell bäibréngt, wéi en eng bestëmmt Aufgab erfëllt. E follegt dem oppenen Agent Skills-Format: eng Datei SKILL.md mat engem Numm an enger Beschreiwung, plus all Scripten, Virlagen oder Referenzdateien, déi de Modell eventuell brauch. De Modell liest d'Instruktiounen eréischt, wann Är Ufro zum Skill passt. En installéierte Skill kascht also näischt, bis e benotzt gëtt.

Wéi ënnerscheede sech KI-Skills vu Plugins oder MCP-Serveren?

E Plugin oder MCP-Server gëtt engem Modell nei Tools, déi en opruffe kann – Code, deen iergendwou leeft an e Resultat zeréckgëtt. E KI-Skill gëtt dem Modell dogéint Wëssen an eng Virgoensweis: wéi en eng Aufgab ugeet, wéi eng Schrëtt en nokënnt a wéi eng gutt Ausgab ausgesäit. Skills bestinn aus einfachem Markdown, brauche kee Server, keen API-Schlëssel a keng Lafzäitëmfeld a funktionéiere mat all Modell.

All weisen

Elo Ären eegene KI-Workspace ariichten

Abonnéiert Iech op eisen Newsletter, fir iwwer nei Funktiounen an zukünfteg Gewënnspiller informéiert ze ginn 👇