Build and maintain a project Risk Register per PMBOK 8 Risk Performance Domain. Identify risks, assess probability and impact, define response strategies, and track residual risk. Use throughout the project lifecycle — not just at planning. Do not use for operational incident response or security vulnerability scanning.

Visão geral

Publicado porhoavdc
RepositórioCodexKit
Nome da habilidadecodexkit-risk-register
Estrelas
27
Forks
12
Arquivos incluídos
1
LicençaMIT
Links
  • Instruções em Markdown

    Um arquivo SKILL.md que o modelo carrega sob demanda, consumindo tokens apenas quando uma solicitação é realmente relevante para a habilidade.

  • Funciona com qualquer LLM

    Habilidades de IA são Markdown simples, não código específico de um provedor, por isso funcionam com GPT, Claude, Gemini, Grok ou um modelo local.

  • 1 arquivos incluídos

    Scripts, modelos de documentos e referências que o modelo pode ler enquanto trabalha. Os arquivos são somente leitura e nunca são executados.

  • Código aberto

    Publicada por hoavdc no GitHub. Leia o conteúdo-fonte antes de instalar.

Instalação

Instale a habilidade de IA Codexkit Risk Register no TypingMind para usá-la com qualquer LLM ou adicione-a a outro agente que leia SKILL.md.

1

Instalar no TypingMind

O TypingMind instala uma habilidade diretamente da pasta dela no GitHub — lê o arquivo SKILL.md, reúne os arquivos de recursos em um pacote e armazena o resultado localmente.

  1. Abra o app e vá para Plugins → Habilidades.
  2. Escolha "Instalar do GitHub".
  3. Cole a URL da pasta da habilidade exibida abaixo e confirme.
    https://github.com/hoavdc/CodexKit/tree/main/skills/codexkit-risk-register
  4. Ative a habilidade em cada chat em que quiser disponibilizá-la.
Plugins → Habilidades → Nova habilidade → Via URL GitHub, depois cole a URL da pasta e pressione Continuar.
2

Instalar em outro agente

Qualquer agente que leia o formato Agent Skills pode usar esta habilidade — copie a pasta para o diretório de habilidades desse agente.

Claude Code — .claude/skills
git clone --depth 1 https://github.com/hoavdc/CodexKit.git /tmp/CodexKit
mkdir -p .claude/skills
cp -r /tmp/CodexKit/skills/codexkit-risk-register .claude/skills/codexkit-risk-register
Reinicie Claude Code após copiar para que a nova habilidade seja reconhecida.

Use no TypingMind

Ative Codexkit Risk Register em qualquer chat do TypingMind e o modelo cuida do resto. O nome e a descrição da habilidade ficam no prompt do sistema e, assim que uma solicitação relevante aparece, o modelo carrega as instruções completas automaticamente — sem precisar de acionamento manual e sem consumir tokens até que ela seja realmente usada.

O modelo carrega Codexkit Risk Register automaticamente assim que uma solicitação é relevante para essa habilidade.

Funciona com qualquer modelo de IA

Habilidades de IA são instruções em Markdown simples, não código específico de um provedor. Por isso, Codexkit Risk Register não fica vinculada ao modelo para o qual foi criada. Instale-a uma vez no TypingMind e use-a com GPT-5, Claude, Gemini, Grok, DeepSeek, Mistral, Llama ou um modelo local executado por conta própria — tudo com suas próprias chaves de API.

  • Carregada apenas quando necessário

    O prompt do sistema contém apenas o nome e a descrição. As instruções são buscadas na primeira solicitação relevante, então uma habilidade sem uso não gera custo.

  • Troque de modelo durante a conversa

    Como a habilidade é composta de instruções, não de código, trocar de modelo não afeta seu funcionamento — o próximo modelo lê o mesmo arquivo SKILL.md.

Instruções da habilidade

Este é o conteúdo de SKILL.md que o modelo carrega. Leia antes de instalar — uma habilidade é um conjunto de instruções que seu modelo seguirá.

Risk Register Manager

Purpose

Systematically identify, assess, and manage project risks using a structured register with probability/impact scoring and defined response strategies.

When to use

  • project kick-off to establish the initial risk baseline
  • sprint or milestone reviews to update and add emerging risks
  • before major decisions to assess risk exposure
  • when stakeholders request a risk assessment report

When not to use

  • live incident response or post-mortem analysis
  • security vulnerability scanning (use security tools)
  • personal task risk assessment

Inputs

  • project scope, objectives, and constraints
  • project type (predictive / adaptive / hybrid)
  • stakeholder list and their risk tolerance
  • known assumptions and dependencies
  • lessons learned from similar projects (if available)

Procedure

  1. Identify risks using multiple sources:
    • Internal: technical complexity, resource gaps, schedule pressure, budget
    • External: market shifts, regulatory changes, vendor reliability, geopolitical
    • PMBOK 8 emphasis: sustainability risks (ESG, climate, social impact)
    • Techniques: brainstorming, PESTLE analysis, Risk Breakdown Structure (RBS)
  2. Assess each risk qualitatively:
    • Probability: Very Low (0.1) / Low (0.3) / Medium (0.5) / High (0.7) / Very High (0.9)
    • Impact: Very Low (0.05) / Low (0.1) / Medium (0.2) / High (0.4) / Very High (0.8)
    • Risk Score = Probability × Impact
    • Red zone (≥ 0.25): immediate response required
    • Yellow zone: response plan needed
    • Green zone: monitor only
  3. Define response strategy:
    • For threats: Avoid / Transfer / Mitigate / Accept (active or passive)
    • For opportunities: Exploit / Share / Enhance / Accept
  4. Assign ownership — every risk has one named owner.
  5. Track residual risk — after response, re-score to verify reduction.
  6. SAFe integration — for SAFe teams, use ROAM board:
    • R = Resolved | O = Owned | A = Accepted | M = Mitigated

Output

  • risk register table: ID | Category | Description | Trigger | Probability | Impact | Score | Owner | Response Strategy | Residual Risk | Status
  • risk heat map summary (red/yellow/green distribution)
  • top 10 risks with detailed response plans
  • escalation list for sponsor or steering committee
  • risk trend over time (risk burn-down if tracked across sprints)

Definition of done

  • every identified risk has a probability, impact, and score
  • every red/yellow risk has a named owner and defined response strategy
  • residual risk is assessed for all mitigated risks
  • register is reviewable by stakeholders

Examples

  • "Build an initial risk register for a 6-month ERP migration project."
  • "Update the risk register after Sprint 5 — add 3 new risks we discovered."
  • "We have 15 risks but no response plans. Help me define strategies for the top 10."

Quality Criteria

  • All dependencies and prerequisites are documented
  • Changes are reversible or include a rollback plan
  • Security implications are assessed for each configuration change
  • Monitoring and alerting are defined for post-deployment validation

Verification (4C)

CheckQuestion
CorrectnessAre all configurations, permissions, and dependencies accurate?
CompletenessDoes the setup cover dev, staging, and prod environments as needed?
Context-fitIs the solution proportional to the problem (not over/under-engineered)?
ConsequenceIf deployed as-is to production, what is the highest-risk failure mode?

Edge Cases

  • Target environment has pre-existing configuration — Scan for conflicts before applying changes. Document what to preserve.
  • Permissions differ between environments — Test in staging first. Document the minimum permissions required.
  • Third-party service is unavailable or deprecated — Document fallback or alternative. Include health-check endpoints.

Changelog

  • v1.0.0 — Initial release

Arquivos incluídos

O modelo lê esses arquivos sob demanda enquanto a habilidade está carregada. Eles são disponibilizados para leitura e nunca são executados.

Perguntas frequentes

O que a habilidade de IA Codexkit Risk Register faz?

Build and maintain a project Risk Register per PMBOK 8 Risk Performance Domain. Identify risks, assess probability and impact, define response strategies, and track residual risk. Use throughout the project lifecycle — not just at planning. Do not use for operational incident response or security vulnerability scanning.

Por que usar Codexkit Risk Register no TypingMind?

Porque basta instalar uma vez para usar com qualquer modelo. Codexkit Risk Register é escrito em Markdown simples, e não em código específico de um provedor, então a mesma habilidade funciona com GPT-5, Claude, Gemini, Grok ou um modelo local — e é possível trocar de modelo no meio do chat sem que ela deixe de funcionar. O TypingMind usa suas próprias chaves de API, então o pagamento é feito diretamente aos provedores, em vez de uma assinatura por licença de usuário, e suas habilidades e chats permanecem no seu próprio armazenamento.

Como instalar Codexkit Risk Register no TypingMind?

Abra Plugins → Habilidades → Instalar do GitHub no TypingMind e cole https://github.com/hoavdc/CodexKit/tree/main/skills/codexkit-risk-register. O TypingMind lê o arquivo SKILL.md, reúne os arquivos da habilidade e a instala para que possa ser ativada em cada chat.

Quais modelos de IA podem usar Codexkit Risk Register?

Qualquer modelo conectado no TypingMind. As habilidades de IA são instruções em Markdown simples, e não código específico de um provedor. Assim, GPT, Claude, Gemini, Grok e modelos locais podem carregar esta habilidade quando uma solicitação corresponder a ela.

Quantos modelos de IA posso usar com Codexkit Risk Register?

Quantos quiser. Desde que o modelo ofereça suporte a habilidades, é possível usar Codexkit Risk Register com ele — GPT, Claude, Gemini, Grok, DeepSeek, Mistral, Llama e outros — tudo no TypingMind com suas próprias chaves de API.

A habilidade de IA Codexkit Risk Register é gratuita?

Sim. A habilidade é publicada no GitHub por hoavdc sob a licença MIT. O pagamento é feito apenas ao seu provedor de IA pelos tokens usados.

O que são habilidades de IA?

Uma habilidade de IA é um conjunto reutilizável de instruções que ensina um modelo de IA a realizar uma tarefa específica. Ela segue o formato aberto Agent Skills: um arquivo SKILL.md com nome e descrição, além de scripts, modelos de documento ou arquivos de referência de que o modelo possa precisar. O modelo lê as instruções apenas quando sua solicitação corresponde à habilidade, então uma habilidade instalada não gera custos até ser usada.

Qual é a diferença entre habilidades de IA e plugins ou servidores MCP?

Um plugin ou servidor MCP oferece ao modelo novas ferramentas para chamar — código que é executado em algum lugar e retorna um resultado. Já uma habilidade de IA fornece conhecimento e um processo ao modelo: como abordar uma tarefa, quais etapas seguir e como deve ser um bom resultado. As habilidades são escritas em Markdown simples, por isso não precisam de servidor, chave de API nem ambiente de execução, e funcionam com qualquer modelo.

Ver todos

Crie seu próprio espaço de IA agora

Inscreva-se na nossa newsletter para receber novidades sobre recursos e futuros sorteios 👇